19906 W SATICOY ST 91306
Certificate Information: 19906 W SATICOY ST 91306
- Application / Permit
- 20014-20000-01687
- Plan Check / Job No.
- B20VN05796
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE (E) FRONT PORCH, ADDITION TO THE FRONT AND REAR (196 SF IN TOTAL) OF (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Valley
- Current Status
- Issued on 8/9/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | SEAN SHAHMIRI |
| Corrections Issued | 5/8/2020 | SEAN SHAHMIRI |
| Green Plans Picked Up | 5/20/2020 | APPLICANT |
| Quality Review Completed | 5/22/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 5/29/2020 | APPLICANT |
| Applicant returned to address corrections | 11/23/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 4/19/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 6/21/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 6/21/2021 | SEAN SHAHMIRI |
| Issued | 8/9/2021 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 10/1/2020 | AARON COSTA |
| Low Impact Development | Cleared | 10/29/2020 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 11/16/2020 | WALLIE JONG |
| Sewer availability | Cleared | 11/16/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/1/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 10/28/2022 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 10/28/2022 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 11/3/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 11/3/2022 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 11/22/2022 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 11/22/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/28/2022 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 12/28/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 1/25/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 2/6/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 3/7/2023 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 6/9/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 6/9/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 6/9/2023 | Approved | ALEXANDER HANDY |
| Insulation | 7/11/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 9/1/2023 | Not Ready for Inspection | MORRIS JACKSON |
| Drywall Nailing | 9/8/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 9/8/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 2/27/2025 | Approved | ALEXANDER HANDY |
| Final | 2/27/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 2/27/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 2/27/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 2/27/2025 | Approved | ALEXANDER HANDY |
| Final | 8/13/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Final | 8/13/2025 | Approved | ALEXANDER HANDY |