14751 W HAGAR ST 91345

Certificate Information: 14751 W HAGAR ST 91345

Application / Permit
20014-20000-01674
Plan Check / Job No.
B20VN05751
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 20' X 24'-6" TO (E) 18' X 20' DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT. WORK PER WFPP.
Permit Issued
Issued on 8/10/2020
Issuing Office
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2020 APPLICANT
Assigned to Plan Check Engineer 5/15/2020 JEROME MAGAT PALMA
Corrections Issued 5/19/2020 JEROME MAGAT PALMA
Applicant returned to address corrections 6/18/2020 ROSENDO MEDINA
Plan Check Approved 8/10/2020 ROSENDO MEDINA
Issued 8/10/2020 APPLICANT
CofO in Progress 3/22/2021 JENNIFER RABUCHIN
CofO Issued 5/1/2021 MICHAEL SMITH
Permit Finaled 5/1/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/29/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/1/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 7/15/2020 MITESH PATEL
Construction within easement Cleared 7/21/2020 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 7/23/2020 ADRIAN CASTRO
Sewer availability Cleared 7/23/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/4/2020 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 9/17/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/5/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/5/2020 Corrections Issued JENNIFER RABUCHIN
Gas Test 11/5/2020 Partial Approval JENNIFER RABUCHIN
Green Building Rough 11/5/2020 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 11/5/2020 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 11/5/2020 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 11/5/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/10/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 11/10/2020 Approved JENNIFER RABUCHIN
Insulation 11/12/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/12/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 11/19/2020 Approved JENNIFER RABUCHIN
Shower Pan 11/19/2020 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 12/3/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 1/5/2021 Approved JENNIFER RABUCHIN
Gas Test 1/5/2021 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 1/5/2021 Partial Inspection MICHAEL TEMPLE
Underground Mechanical 1/5/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/6/2021 Approved JENNIFER RABUCHIN
Sewer 1/8/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/19/2021 Approved JENNIFER RABUCHIN
Final 1/19/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/19/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 1/19/2021 Approved JENNIFER RABUCHIN
MERV13>=Final 1/19/2021 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 1/19/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/19/2021 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 1/19/2021 Approved JENNIFER RABUCHIN
Final 2/12/2021 Partial Approval JENNIFER RABUCHIN
Green Building Final 2/12/2021 Approved JENNIFER RABUCHIN
MERV13>=Final 2/12/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/12/2021 SGSOV Approved JENNIFER RABUCHIN
Final 2/17/2021 Corrections Issued MICHAEL TEMPLE
Final 3/17/2021 Conditional Approval MICHAEL TEMPLE
ELECTRICAL-Final 3/22/2021 Approved JENNIFER RABUCHIN
Final 3/22/2021 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 3/22/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/22/2021 Approved JENNIFER RABUCHIN