14751 W HAGAR ST 91345
Certificate Information: 14751 W HAGAR ST 91345
- Application / Permit
- 20014-20000-01674
- Plan Check / Job No.
- B20VN05751
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 20' X 24'-6" TO (E) 18' X 20' DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT. WORK PER WFPP.
- Permit Issued
- Issued on 8/10/2020
- Issuing Office
- Current Status
- CofO Issued on 5/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 5/19/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 6/18/2020 | ROSENDO MEDINA |
| Plan Check Approved | 8/10/2020 | ROSENDO MEDINA |
| Issued | 8/10/2020 | APPLICANT |
| CofO in Progress | 3/22/2021 | JENNIFER RABUCHIN |
| CofO Issued | 5/1/2021 | MICHAEL SMITH |
| Permit Finaled | 5/1/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 7/15/2020 | MITESH PATEL |
| Construction within easement | Cleared | 7/21/2020 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 7/23/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/23/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/4/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/17/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/5/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/5/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 11/5/2020 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 11/5/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 11/5/2020 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 11/5/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/5/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/10/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 11/10/2020 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/12/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/12/2020 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/19/2020 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 11/19/2020 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/3/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/5/2021 | Approved | JENNIFER RABUCHIN |
| Gas Test | 1/5/2021 | Partial Approval | JENNIFER RABUCHIN |
| Pre-Inspection | 1/5/2021 | Partial Inspection | MICHAEL TEMPLE |
| Underground Mechanical | 1/5/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/6/2021 | Approved | JENNIFER RABUCHIN |
| Sewer | 1/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/19/2021 | Approved | JENNIFER RABUCHIN |
| Final | 1/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 1/19/2021 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 1/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 1/19/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/19/2021 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 1/19/2021 | Approved | JENNIFER RABUCHIN |
| Final | 2/12/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 2/12/2021 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 2/12/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 2/17/2021 | Corrections Issued | MICHAEL TEMPLE |
| Final | 3/17/2021 | Conditional Approval | MICHAEL TEMPLE |
| ELECTRICAL-Final | 3/22/2021 | Approved | JENNIFER RABUCHIN |
| Final | 3/22/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 3/22/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/22/2021 | Approved | JENNIFER RABUCHIN |