1355 1/2 S MEADOWBROOK AVE 90019

Certificate Information: 1355 1/2 S MEADOWBROOK AVE 90019

Application / Permit
20014-20000-01659
Plan Check / Job No.
B20VN05720
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18" X 24' DETACHED GARAGE AND ADD 14'-2" X 21' TO CREATE (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/21/2020
Issuing Office
Current Status
CofO Issued on 6/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/24/2020 RAPHAEL ROSAS
Corrections Issued 4/24/2020 RAPHAEL ROSAS
Applicant returned to address corrections 6/18/2020 ROSENDO MEDINA
Plan Check Approved 9/8/2020 RAPHAEL ROSAS
Issued 9/21/2020 APPLICANT
CofO in Progress 5/23/2021 STUART CHAPMAN
Permit Finaled 6/29/2021 DEROLD HAUFF
CofO Issued 6/29/2021 DEROLD HAUFF
Permit Finaled 6/29/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/1/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/6/2020 RENZ SORIANO
Address approval Cleared 7/7/2020 RENZ SORIANO
Sewer availability Cleared 7/8/2020 RENZ SORIANO
Construction near power lines Cleared 8/22/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 8/31/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/24/2020 Partial Inspection DAVID CHAN
Pre-Inspection 10/28/2020 Partial Inspection DAVID CHAN
Pre-Inspection 11/9/2020 Partial Inspection DAVID CHAN
Footing/Foundation/Slab 11/16/2020 Partial Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 11/20/2020 Partial Approval DAVID CHAN
METHANE-Barrier 11/25/2020 Not Ready for Inspection DAVID CHAN
METHANE-Subgrade 11/25/2020 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 12/1/2020 Approved DAVID CHAN
METHANE-Barrier 12/1/2020 Approved DAVID CHAN
METHANE-Subgrade 12/1/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 12/8/2020 Not Ready for Inspection DAVID CHAN
METHANE-Rough 12/8/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 12/14/2020 Approved DAVID CHAN
Wood Frame 12/14/2020 Approved DAVID CHAN
ELECTRICAL-Rough 12/18/2020 Not Ready for Inspection DAVID CHAN
HVAC-Rough 12/18/2020 Not Ready for Inspection DAVID CHAN
PLUMBING-Rough 12/18/2020 Not Ready for Inspection DAVID CHAN
ELECTRICAL-Rough 12/28/2020 Corrections Issued STUART CHAPMAN
HVAC-Rough 12/28/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 12/28/2020 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 12/31/2020 Approved CHRIS CHRISTENSEN
HVAC-Rough 12/31/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 12/31/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/6/2021 Not Ready for Inspection DAVID CHAN
HVAC-Rough 1/6/2021 Approved DAVID CHAN
PLUMBING-Rough 1/6/2021 Approved DAVID CHAN
BUILDING-Rough-Frame 2/8/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 2/8/2021 Not Ready for Inspection STUART CHAPMAN
Insulation 2/8/2021 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 2/8/2021 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 2/10/2021 Approved SCOTT FINNILA
Green Building Rough 2/10/2021 Approved SCOTT FINNILA
Insulation 2/10/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 2/10/2021 Conditional Approval SCOTT FINNILA
Drywall Nailing 2/19/2021 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 2/19/2021 Not Ready for Inspection JOSEPH MCGARRY
Drywall Nailing 2/25/2021 Approved JOSEPH MCGARRY
Shower Pan 2/25/2021 Not Ready for Inspection JOSEPH MCGARRY
Gas Test 3/3/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/3/2021 Approved STUART CHAPMAN
Shower Pan 3/3/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 5/11/2021 Corrections Issued CHRIS CHRISTENSEN
Final 5/11/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Final 5/11/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 5/11/2021 Conditional Approval CHRIS CHRISTENSEN
PLUMBING-Final 5/11/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/11/2021 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 5/11/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 5/19/2021 Approved STUART CHAPMAN
Final 5/19/2021 OK to Issue CofO STUART CHAPMAN
Green Building Final 5/19/2021 Approved STUART CHAPMAN
HVAC-Final 5/19/2021 Approved STUART CHAPMAN
PLUMBING-Final 5/19/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Approved STUART CHAPMAN
Service/Power Release 5/19/2021 Approved STUART CHAPMAN