12614 W GILMORE ST 91606
Certificate Information: 12614 W GILMORE ST 91606
- Application / Permit
- 20014-20000-01654
- Plan Check / Job No.
- B20VN05714
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 17'-0" X 15'-6" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 9/16/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 4/27/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/27/2020 | JEROME MAGAT PALMA |
| Issued | 9/16/2020 | APPLICANT |
| CofO in Progress | 8/27/2021 | CHRISTOPHE COCHRAN |
| Permit Finaled | 10/26/2021 | MICHAEL SMITH |
| CofO Issued | 10/26/2021 | MICHAEL SMITH |
| Permit Finaled | 10/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| ZA Case | Cleared | 5/6/2020 | MIGUEL GAMBOA |
| Address approval | Cleared | 5/7/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 5/7/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/8/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 8/17/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/2/2020 | Partial Approval | MATTHEW NELSON |
| Sewer | 11/2/2020 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/13/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/23/2020 | Approved | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2020 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2021 | Not Ready for Inspection | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 1/4/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2021 | Approved | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 1/7/2021 | Corrections Issued | DANIEL DREW |
| BUILDING-Rough-Frame | 1/11/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/11/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/11/2021 | Approved | MATTHEW NELSON |
| Insulation | 1/11/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 1/11/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2021 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 1/21/2021 | Approved | BRENDAN LOONEY |
| Shower Pan | 2/1/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/5/2021 | Approved | BRENDAN LOONEY |
| Final | 3/1/2021 | Corrections Issued | JOHN HAYES |
| Service/Power Release | 3/1/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 3/9/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 4/28/2021 | Corrections Issued | DANIEL ORRANTE |
| ELECTRICAL-Final | 5/13/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 5/13/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/13/2021 | SGSOV Not Ready | RICHARD DOCKUS |
| Final | 8/25/2021 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 8/25/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 8/25/2021 | Approved | ARAM AVEDISIAN |
| Final | 8/27/2021 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/3/2021 | Approved | CHRISTOPHE COCHRAN |