12614 W GILMORE ST 91606

Certificate Information: 12614 W GILMORE ST 91606

Application / Permit
20014-20000-01654
Plan Check / Job No.
B20VN05714
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
17'-0" X 15'-6" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 9/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/24/2020 JEROME MAGAT PALMA
Corrections Issued 4/27/2020 JEROME MAGAT PALMA
Plan Check Approved 8/27/2020 JEROME MAGAT PALMA
Issued 9/16/2020 APPLICANT
CofO in Progress 8/27/2021 CHRISTOPHE COCHRAN
Permit Finaled 10/26/2021 MICHAEL SMITH
CofO Issued 10/26/2021 MICHAEL SMITH
Permit Finaled 10/26/2021 MICHAEL SMITH

Permit Application Clearance Information

ZA Case Cleared 5/6/2020 MIGUEL GAMBOA
Address approval Cleared 5/7/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 5/7/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/8/2020 GUILLERMO PETRA
Sewer availability Cleared 5/8/2020 GUILLERMO PETRA
Construction near power lines Cleared 8/17/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/2/2020 Partial Approval MATTHEW NELSON
Sewer 11/2/2020 Partial Inspection MATTHEW NELSON
Footing/Foundation/Slab 11/13/2020 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/23/2020 Approved BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 12/9/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/4/2021 Not Ready for Inspection DANIEL DREW
Rough-Elec/Plmb/HVAC 1/4/2021 Not Ready for Inspection DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Approved DANIEL DREW
Rough-Elec/Plmb/HVAC 1/7/2021 Corrections Issued DANIEL DREW
BUILDING-Rough-Frame 1/11/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 1/11/2021 Approved MATTHEW NELSON
Green Building Rough 1/11/2021 Approved MATTHEW NELSON
Insulation 1/11/2021 Approved MATTHEW NELSON
PLUMBING-Rough 1/11/2021 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Approved BRENDAN LOONEY
Drywall Nailing 1/21/2021 Approved BRENDAN LOONEY
Shower Pan 2/1/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 2/5/2021 Approved BRENDAN LOONEY
Final 3/1/2021 Corrections Issued JOHN HAYES
Service/Power Release 3/1/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 3/9/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 4/28/2021 Corrections Issued DANIEL ORRANTE
ELECTRICAL-Final 5/13/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Final 5/13/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 5/13/2021 SGSOV Not Ready RICHARD DOCKUS
Final 8/25/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 8/25/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 8/25/2021 Approved ARAM AVEDISIAN
Final 8/27/2021 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 9/3/2021 Approved CHRISTOPHE COCHRAN