6569 N CLEOMOORE AVE 91307
Certificate Information: 6569 N CLEOMOORE AVE 91307
- Application / Permit
- 20014-20000-01651
- Plan Check / Job No.
- B20VN05710
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD IRREGULAR 23' X 26' FOR NEW MASTER BEDROOM/BATHROOM/CLOSET AND LAUNDRY ROOM, ADD 3'-6" X 3'-9" ENTRY TO (E) SFD. ALL WORK PER DESIGN.
- Permit Issued
- Issued on 6/12/2020
- Issuing Office
- Current Status
- CofO Issued on 3/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2020 | ALFREDO JARA |
| Corrections Issued | 4/23/2020 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 4/30/2020 | APPLICANT |
| Plan Check Approved | 6/11/2020 | JENNIFER LEE |
| Issued | 6/12/2020 | APPLICANT |
| CofO in Progress | 3/9/2021 | TROY SANDERS |
| Permit Finaled | 3/9/2021 | JOHN JANSON |
| CofO Issued | 3/9/2021 | JOHN JANSON |
| Permit Finaled | 3/9/2021 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/29/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/1/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/1/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 6/3/2020 | JAHANSHAH POURHASSAN |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/10/2020 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 7/13/2020 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 7/13/2020 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 7/15/2020 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/12/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 8/12/2020 | Approved | TROY SANDERS |
| Green Building Rough | 8/12/2020 | Approved | TROY SANDERS |
| HVAC-Rough | 8/12/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 8/12/2020 | Approved | TROY SANDERS |
| Insulation | 8/14/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 8/18/2020 | Approved | TROY SANDERS |
| Drywall Nailing | 8/26/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 8/26/2020 | Approved | TROY SANDERS |
| Shower Pan | 8/26/2020 | Approved | TROY SANDERS |
| Final | 2/8/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 2/8/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 2/8/2021 | Approved | TROY SANDERS |
| Final | 3/9/2021 | OK to Issue CofO | TROY SANDERS |