6899 N LINDLEY AVE 91335
Certificate Information: 6899 N LINDLEY AVE 91335
- Application / Permit
- 20014-20000-01631
- Plan Check / Job No.
- B20VN05644
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 41'-1" X 21' TO AND CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 7/9/2020
- Issuing Office
- Current Status
- CofO Issued on 12/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | SELLA BENYAMIN |
| Corrections Issued | 5/13/2020 | SELLA BENYAMIN |
| Quality Review Completed | 5/19/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/20/2020 | APPLICANT |
| Green Plans Picked Up | 5/20/2020 | APPLICANT |
| Plan Check Approved | 6/26/2020 | SELLA BENYAMIN |
| Issued | 7/9/2020 | APPLICANT |
| CofO in Progress | 12/6/2021 | VINCENT HANLEY |
| CofO Issued | 12/18/2021 | MICHAEL SMITH |
| Permit Finaled | 12/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 5/26/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 6/2/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 6/17/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/22/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 6/25/2020 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Ali Reza; Lic. No.: C87661 | 20655 SHERMAN WAY #5 LOS ANGELES, CA 91306 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2020 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 8/14/2020 | Corrections Issued | VINCENT HANLEY |
| Sewer | 8/14/2020 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 8/17/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 8/17/2020 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 9/2/2020 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/18/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/4/2020 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 12/4/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 1/20/2021 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 1/20/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/8/2021 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 3/8/2021 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 3/8/2021 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/25/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 3/25/2021 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 3/25/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/8/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/8/2021 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/13/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 5/13/2021 | Approved | VINCENT HANLEY |
| Final | 7/6/2021 | No Access for Inspection | VINCENT HANLEY |
| Green Building Final | 7/6/2021 | No Access for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/6/2021 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 7/6/2021 | No Access for Inspection | VINCENT HANLEY |
| Smoke Detectors | 7/6/2021 | No Access for Inspection | VINCENT HANLEY |
| Final | 8/18/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 10/1/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 10/1/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 10/20/2021 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 10/20/2021 | Approved | VINCENT HANLEY |
| Final | 11/23/2021 | Not Ready for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 11/23/2021 | No Access for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 12/6/2021 | Approved | VINCENT HANLEY |
| Final | 12/6/2021 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 12/6/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 12/6/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 12/6/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/6/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 12/6/2021 | Approved | VINCENT HANLEY |