10742 N GERALD AVE 91344

Certificate Information: 10742 N GERALD AVE 91344

Application / Permit
20014-20000-01630
Plan Check / Job No.
B20VN05637
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED (E) GARAGE TO (N) ACCESSORY DWELLING UNIT AND ENLARGE IT TO 22'-3" x 23'-6" AND ADD 2ND FLOOR TO NEW ADU.
Permit Issued
Issued on 2/13/2022
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 SEAN SHAHMIRI
Corrections Issued 5/14/2020 SEAN SHAHMIRI
Green Plans Picked Up 6/3/2020 APPLICANT
Quality Review Completed 6/5/2020 OMID HEDAYAT
Building Plans Picked Up 6/11/2020 APPLICANT
Applicant returned to address corrections 10/6/2020 SEAN SHAHMIRI
Plan Check Approved 10/6/2020 SEAN SHAHMIRI
Issued 2/13/2022 APPLICANT
CofO in Progress 10/29/2025 CHRISTOPHER ROJAS
Permit Finaled 11/18/2025 RUBEN SALAS
CofO Issued 11/18/2025 RUBEN SALAS
Permit Finaled 11/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/20/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/21/2020 ADRIAN CASTRO
Sewer availability Cleared 5/21/2020 ADRIAN CASTRO
Low Impact Development Cleared 8/16/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/21/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 9/22/2020 MATTHEW CRAIG
Green Code Cleared 9/25/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 21520 BURBANK BLVD APT 219      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/9/2024 No Access for Inspection JAVIER RAMOS JR
Pre-Inspection 7/12/2024 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 7/31/2024 Partial Inspection JAVIER RAMOS JR
Pre-Inspection 8/7/2024 Partial Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 8/26/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 8/26/2024 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 9/3/2024 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 9/4/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/18/2024 Partial Approval MATTHEW NELSON
Green Building Rough 9/18/2024 Not Ready for Inspection MATTHEW NELSON
Sewer 10/2/2024 Approved JAVIER RAMOS JR
Underground Mechanical 10/2/2024 Partial Approval JAVIER RAMOS JR
Wood Frame 10/7/2024 Partial Approval KEVIN BERBERYAN
PLUMBING-Rough 10/15/2024 Approved JAVIER RAMOS JR
Sewer 10/18/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/1/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 11/1/2024 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 11/12/2024 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 11/22/2024 Partial Approval MICHAEL CORTEZ
Insulation 11/22/2024 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 12/10/2024 Corrections Issued LOUIS ESCOTO
Green Building Rough 12/10/2024 Corrections Issued LOUIS ESCOTO
Interior/Exterior Lathing 12/10/2024 Approved LOUIS ESCOTO
Shower Pan 12/10/2024 Corrections Issued LOUIS ESCOTO
Drywall Nailing 12/26/2024 Approved MICHAEL CORTEZ
Green Building Rough 12/26/2024 Approved MICHAEL CORTEZ
Shower Pan 12/26/2024 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 8/19/2025 Corrections Issued CHRISTOPHER ROJAS
Final 8/19/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/19/2025 Approved CHRISTOPHER ROJAS
Green Building Final 8/19/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 8/19/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 8/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Inspection 8/29/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/18/2025 Approved NICHOLAS TROWBRIDGE
Final 9/18/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Final 9/18/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 10/28/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 10/28/2025 Approved CHRISTOPHER ROJAS