10742 N GERALD AVE 91344
Certificate Information: 10742 N GERALD AVE 91344
- Application / Permit
- 20014-20000-01630
- Plan Check / Job No.
- B20VN05637
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED (E) GARAGE TO (N) ACCESSORY DWELLING UNIT AND ENLARGE IT TO 22'-3" x 23'-6" AND ADD 2ND FLOOR TO NEW ADU.
- Permit Issued
- Issued on 2/13/2022
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | SEAN SHAHMIRI |
| Corrections Issued | 5/14/2020 | SEAN SHAHMIRI |
| Green Plans Picked Up | 6/3/2020 | APPLICANT |
| Quality Review Completed | 6/5/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 6/11/2020 | APPLICANT |
| Applicant returned to address corrections | 10/6/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 10/6/2020 | SEAN SHAHMIRI |
| Issued | 2/13/2022 | APPLICANT |
| CofO in Progress | 10/29/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
| CofO Issued | 11/18/2025 | RUBEN SALAS |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/21/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 8/16/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/21/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 9/22/2020 | MATTHEW CRAIG |
| Green Code | Cleared | 9/25/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 21520 BURBANK BLVD APT 219 WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2024 | No Access for Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 7/12/2024 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 7/31/2024 | Partial Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 8/7/2024 | Partial Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/26/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/26/2024 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 9/3/2024 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/4/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/18/2024 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 9/18/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Sewer | 10/2/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 10/2/2024 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 10/7/2024 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/15/2024 | Approved | JAVIER RAMOS JR |
| Sewer | 10/18/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/1/2024 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 11/1/2024 | Partial Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/12/2024 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 11/22/2024 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 11/22/2024 | Corrections Issued | MICHAEL CORTEZ |
| Drywall Nailing | 12/10/2024 | Corrections Issued | LOUIS ESCOTO |
| Green Building Rough | 12/10/2024 | Corrections Issued | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/10/2024 | Approved | LOUIS ESCOTO |
| Shower Pan | 12/10/2024 | Corrections Issued | LOUIS ESCOTO |
| Drywall Nailing | 12/26/2024 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 12/26/2024 | Approved | MICHAEL CORTEZ |
| Shower Pan | 12/26/2024 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 8/19/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 8/19/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 8/19/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 8/19/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/19/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 8/19/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 8/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 8/29/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 9/18/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Final | 9/18/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 10/28/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 10/28/2025 | Approved | CHRISTOPHER ROJAS |