4545 N LIBBIT AVE 91436

Certificate Information: 4545 N LIBBIT AVE 91436

Application / Permit
20014-20000-01625
Plan Check / Job No.
B20VN05628
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
4' X 6'-4" & 10'-1" X 2'-5" ADDITION TO (E) 2-STORY SINGLE FAMILY DWELLING AND ENCLOSE 6'-7" X 22'-10" PATIO.
Permit Issued
Issued on 11/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2020 APPLICANT
Assigned to Plan Check Engineer 5/24/2020 SERGIO MUNIZ
Corrections Issued 5/27/2020 SERGIO MUNIZ
Green Plans Picked Up 6/1/2020 APPLICANT
Quality Review Completed 6/19/2020 STEVEN KIM
Building Plans Picked Up 6/25/2020 APPLICANT
Plan Check Approved 10/21/2020 SERGIO MUNIZ
Issued 11/13/2020 APPLICANT
CofO in Progress 12/14/2021 ROBERT GOLD
CofO Issued 12/18/2021 MICHAEL SMITH
Permit Finaled 12/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Tract Map conditions Cleared 8/17/2020 VINCENT QUITORIANO
Eng Process Fee Ord 176,300 Cleared 8/18/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 8/18/2020 BRIAN MILLER
Green Code Cleared 8/18/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 8/18/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/25/2020 Approved RONALD COWAN
Footing/Foundation/Slab 12/3/2020 Approved RONALD COWAN
Insulation 12/16/2020 Not Ready for Inspection RONALD COWAN
Underground Mechanical 12/16/2020 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 12/18/2020 Not Ready for Inspection MICHAEL TEMPLE
Green Building Rough 12/18/2020 Not Ready for Inspection MICHAEL TEMPLE
BUILDING-Rough-Frame 12/24/2020 Partial Inspection DAVID SANDOVAL
Underground Mechanical 12/24/2020 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/11/2021 Partial Approval DAVID SCANTLIN
Green Building Rough 3/11/2021 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 4/6/2021 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 4/6/2021 Approved RONALD COWAN
Green Building Rough 4/6/2021 Corrections Issued RONALD COWAN
PLUMBING-Rough 4/6/2021 Approved RONALD COWAN
Wood Frame 4/6/2021 Approved RONALD COWAN
HVAC-Rough 4/7/2021 Approved RONALD COWAN
ELECTRICAL-Rough 4/13/2021 No Access for Inspection DAVID SANDOVAL
HVAC-Rough 4/13/2021 No Access for Inspection DAVID SANDOVAL
Insulation 4/13/2021 No Access for Inspection DAVID SANDOVAL
PLUMBING-Rough 4/13/2021 No Access for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 5/5/2021 Approved STEVEN BACK
Green Building Rough 5/5/2021 Approved STEVEN BACK
Insulation 5/5/2021 Approved STEVEN BACK
Shower Pan 5/5/2021 Approved STEVEN BACK
Drywall Nailing 5/14/2021 Approved STEPHANIE SWANSON
Pre-Inspection 5/14/2021 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 11/15/2021 Approved DAVID SANDOVAL
Final 11/15/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 11/15/2021 Approved DAVID SANDOVAL
HVAC-Final 11/15/2021 Approved DAVID SANDOVAL
PLUMBING-Final 11/15/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 11/15/2021 Approved DAVID SANDOVAL
Final 12/13/2021 OK to Issue CofO ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Approved ROBERT GOLD