10501 W RAINIER ST 91352

Certificate Information: 10501 W RAINIER ST 91352

Application / Permit
20014-20000-01623
Plan Check / Job No.
B20VN05623
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 16'6" X 29'-5" FOR NEW EXERCISE ROOM W/ FULL BATH AND LAUNDRY ROOM (NO CLOSET) TO AN (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/24/2020
Issuing Office
Current Status
CofO Issued on 2/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2020 APPLICANT
Assigned to Plan Check Engineer 4/20/2020 LUIS RINCON
Corrections Issued 4/20/2020 LUIS RINCON
Applicant returned to address corrections 5/18/2020 JENNIFER LEE
Applicant returned to address corrections 5/29/2020 HAYATO TSUCHIYA
Plan Check Approved 6/11/2020 JENNIFER LEE
Issued 6/24/2020 APPLICANT
CofO in Progress 2/23/2021 DAVID MATSON
Permit Finaled 2/23/2021 MICHAEL SMITH
CofO Issued 2/23/2021 MICHAEL SMITH
Permit Finaled 2/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/7/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 5/7/2020 GUILLERMO PETRA
Sewer availability Cleared 5/7/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Gallardo,, Samuel Pigao; Lic. No.: C68174 23013 BERENDO AVE      TORRANCE, CA 90502

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/7/2020 Partial Approval JOHN HAYES
Sewer 10/7/2020 Approved JOHN HAYES
Footing/Foundation/Slab 10/15/2020 Approved BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Approved BEAU COLLINS
ELECTRICAL-Rough 12/11/2020 Partial Approval DANIEL DREW
HVAC-Rough 12/11/2020 Approved DANIEL DREW
Shower Pan 12/11/2020 Approved DANIEL DREW
Insulation 12/21/2020 Partial Approval BEAU COLLINS
Drywall Nailing 12/23/2020 Approved JOHN HAYES
Green Building Rough 12/23/2020 Approved JOHN HAYES
BUILDING-Rough-Frame 1/26/2021 Approved BEAU COLLINS
Final 1/26/2021 Corrections Issued BEAU COLLINS
Green Building Final 1/26/2021 Not Ready for Inspection BEAU COLLINS
MERV13>=Final 1/26/2021 Approved BEAU COLLINS
MERV13>=Rough 1/26/2021 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 1/26/2021 SGSOV Approved BEAU COLLINS
Smoke Detectors 1/26/2021 Not Ready for Inspection BEAU COLLINS
Final 2/11/2021 Partial Inspection BEAU COLLINS
Green Building Final 2/11/2021 Approved BEAU COLLINS
Smoke Detectors 2/11/2021 Approved BEAU COLLINS
Final 2/23/2021 OK to Issue CofO DAVID MATSON