8660 N CORBIN AVE 91324

Certificate Information: 8660 N CORBIN AVE 91324

Application / Permit
20014-20000-01604
Plan Check / Job No.
B20VN05581
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE (20'X20') INTO ACCESSORY DWELLING UNIT WITH ADDITION (20'X18'). ALL WORK PER WFPP.
Permit Issued
Issued on 7/2/2020
Issuing Office
Current Status
CofO Issued on 12/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 4/23/2020 HAYATO TSUCHIYA
Corrections Issued 4/23/2020 HAYATO TSUCHIYA
Plan Check Approved 5/14/2020 HAYATO TSUCHIYA
Issued 7/2/2020 APPLICANT
CofO in Progress 12/7/2021 JEFFREY PARD
Permit Finaled 12/7/2021 JOHN JANSON
CofO Issued 12/7/2021 JOHN JANSON
Permit Finaled 12/7/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/28/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 4/28/2020 JOHN LIN
Roof/Waste drainage to street Cleared 4/28/2020 JOHN LIN
Sewer availability Cleared 4/28/2020 JOHN LIN

Contact Information

Contractor Ponce Construction; Lic. No.: 778646-B 22817 VENTURA BLVD.   #987    WOODLAND HILLS, CA 91364

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/8/2020 Corrections Issued JEFFREY PARD
Underground Mechanical 7/8/2020 Corrections Issued JEFFREY PARD
Deputy Drilled-In Anchors 7/10/2020 Approved JEFFREY PARD
PLUMBING-Rough 7/14/2020 Partial Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 7/20/2020 No Access for Inspection JEFFREY PARD
Special/Order Compliance 7/22/2020 Corrections Issued JEFFREY PARD
Excavation/Setback/Form/Re-Bar 8/4/2020 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 8/4/2020 Corrections Issued JEFFREY PARD
Excavation/Setback/Form/Re-Bar 8/6/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Not Ready for Inspection JEFFREY PARD
Wood Frame 9/25/2020 Not Ready for Inspection JEFFREY PARD
Excavation/Setback/Form/Re-Bar 11/12/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 12/2/2020 Approved JEFFREY PARD
HVAC-Rough 12/2/2020 Approved JEFFREY PARD
PLUMBING-Rough 12/2/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/3/2020 No Access for Inspection JEFFREY PARD
Green Building Rough 12/3/2020 No Access for Inspection JEFFREY PARD
BUILDING-Rough-Frame 12/18/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 12/18/2020 Approved JEFFREY PARD
Drywall Nailing 8/18/2021 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 8/18/2021 Approved CHRISTOPHER DELLEFIELD
Shower Pan 8/18/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/8/2021 Approved JEFFREY PARD
Gas Test 10/25/2021 Approved MORRIS JACKSON
Final 10/28/2021 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 10/28/2021 Approved JEFFREY PARD
Green Building Final 10/28/2021 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 10/28/2021 Approved JEFFREY PARD
Final 11/16/2021 Not Ready for Inspection JEFFREY PARD
Green Building Final 11/16/2021 Not Ready for Inspection JEFFREY PARD
Final 12/7/2021 OK to Issue CofO JEFFREY PARD
Green Building Final 12/7/2021 Approved JEFFREY PARD