7405 W HAWTHORN AVE 90046

Certificate Information: 7405 W HAWTHORN AVE 90046

Application / Permit
20014-20000-01601
Plan Check / Job No.
B20VN05576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT WITH ADDITIONS. THIS PERMIT TO INCLUDE REINFORCING EX ROOF FRAMING. SEE COMMENTS
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
CofO Issued on 4/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/21/2020 HAYATO TSUCHIYA
Corrections Issued 4/23/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/22/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 1/5/2021 HAYATO TSUCHIYA
Plan Check Approved 3/4/2021 HAYATO TSUCHIYA
Building Plans Picked Up 3/5/2021 APPLICANT
Issued 3/25/2021 APPLICANT
CofO in Progress 4/1/2022 RAUL BARAJAS
Permit Finaled 4/1/2023 DANIEL ORRANTE
CofO Issued 4/1/2023 DANIEL ORRANTE
Permit Finaled 4/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/18/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 8/18/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/24/2020 WALLIE JONG
Sewer availability Cleared 8/24/2020 WALLIE JONG
HPOZ Cleared 8/27/2020 AMANDA KAINER
Miscellaneous Cleared 8/27/2020 AMANDA KAINER
Specific Plan Cleared 8/27/2020 AMANDA KAINER
Hold Cleared 4/22/2021 JASON SHEETS

Contact Information

Contractor Gaga Builders Inc; Lic. No.: 1038675-B 22287 MULHOLLAND HWY UNIT #194      CALABASAS, CA 91302
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2021 Partial Inspection RAUL BARAJAS
Sewer 5/7/2021 Approved RAUL BARAJAS
Footing/Foundation/Slab 5/13/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 6/9/2021 Approved RAUL BARAJAS
Underground Mechanical 6/9/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 10/4/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 10/4/2021 Approved RAUL BARAJAS
Green Building Rough 10/4/2021 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 10/4/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 11/1/2021 Corrections Issued RAUL BARAJAS
Green Building Rough 11/1/2021 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 11/9/2021 Approved RAUL BARAJAS
Green Building Rough 11/9/2021 Approved RAUL BARAJAS
HVAC-Rough 11/9/2021 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 11/9/2021 Partial Approval RAUL BARAJAS
Insulation 11/17/2021 Approved RAUL BARAJAS
Drywall Nailing 11/23/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 11/23/2021 Approved RAUL BARAJAS
Final 2/17/2022 Corrections Issued RAUL BARAJAS
Green Building Final 2/17/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/17/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 2/17/2022 Approved RAUL BARAJAS
Final 3/15/2022 Corrections Issued RAUL BARAJAS
Final 4/1/2022 OK to Issue CofO RAUL BARAJAS