14925 W FRIAR ST 91411

Certificate Information: 14925 W FRIAR ST 91411

Application / Permit
20014-20000-01596
Plan Check / Job No.
B20VN05562
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 14'10" X 15' ADDITION TO (E) SFD TO ADD NEW BEDROOM , BATHROOM AND W.I.C., NEW 20'9" X 20'7" ADDDITON TO (E) SFD TO AD NEW BEDROOM, BATHROOM AND CLOSET, ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/31/2020
Issuing Office
Current Status
CofO Issued on 7/31/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 RARES BODEA
Corrections Issued 5/12/2020 RARES BODEA
Quality Review Completed 5/14/2020 STEVEN KIM
Building Plans Picked Up 5/15/2020 APPLICANT
Green Plans Picked Up 5/15/2020 APPLICANT
Applicant returned to address corrections 8/31/2020 RARES BODEA
Plan Check Approved 8/31/2020 RARES BODEA
Issued 8/31/2020 APPLICANT
CofO in Progress 7/2/2021 ARTHUR SARGSYAN
CofO in Progress 7/2/2021 ARTHUR SARGSYAN
CofO Issued 7/31/2021 MICHAEL SMITH
Permit Finaled 7/31/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/19/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 5/19/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 6/29/2020 RARES BODEA
Low Impact Development Cleared 7/10/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/22/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Parker Bldg & Concrete; Lic. No.: 744777-B 1075 ELMHURST DR      CORONA, CA 92880
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/29/2020 Approved WILLIAM KUEHN
Underground Mechanical 9/29/2020 Not Ready for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 10/14/2020 Partial Inspection MATTHEW NELSON
PLUMBING-Rough 10/14/2020 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Partial Approval DAVID MATSON
Insulation 10/20/2020 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 12/7/2020 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Approved JENNIFER RABUCHIN
Green Building Rough 12/7/2020 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 12/7/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/22/2020 Not Ready for Inspection DAVID MATSON
Green Building Rough 12/22/2020 No Access for Inspection DAVID MATSON
HVAC-Rough 12/22/2020 Not Ready for Inspection DAVID MATSON
Interior/Exterior Lathing 12/22/2020 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 12/22/2020 Approved DAVID MATSON
Wood Frame 12/22/2020 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 1/8/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/8/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/8/2021 Approved JENNIFER RABUCHIN
Shower Pan 1/8/2021 Approved JENNIFER RABUCHIN
Insulation 1/25/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 1/25/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 2/11/2021 Approved MICHEL ABAJAN
Green Building Rough 2/11/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/15/2021 Approved MICHAEL TEMPLE
Final 4/15/2021 Corrections Issued MICHAEL TEMPLE
Green Building Final 4/15/2021 Not Ready for Inspection MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 4/15/2021 SGSOV Approved MICHAEL TEMPLE
Smoke Detectors 4/15/2021 Corrections Issued MICHAEL TEMPLE
Final 4/26/2021 Partial Inspection MICHAEL TEMPLE
Green Building Final 4/26/2021 Approved MICHAEL TEMPLE
Service/Power Release 4/26/2021 Approved MICHAEL TEMPLE
Smoke Detectors 4/26/2021 Not Ready for Inspection MICHAEL TEMPLE
Final 6/24/2021 OK to Issue CofO ARTHUR SARGSYAN
Smoke Detectors 6/24/2021 Approved ARTHUR SARGSYAN
Service/Power Release 7/7/2021 Not Required ARTHUR SARGSYAN