3068 N TYBURN ST 90039
Certificate Information: 3068 N TYBURN ST 90039
- Application / Permit
- 20014-20000-01589
- Plan Check / Job No.
- B20VN05539
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 13' X 14'-6" ADDITION TO CREATE 2ND-STORY TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT WITH UNCOVERED DECK.
- Permit Issued
- Issued on 7/15/2020
- Issuing Office
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | SERGIO MUNIZ |
| Corrections Issued | 5/6/2020 | SERGIO MUNIZ |
| Quality Review Completed | 5/18/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 5/22/2020 | APPLICANT |
| Green Plans Picked Up | 5/27/2020 | APPLICANT |
| Plan Check Approved | 7/14/2020 | SERGIO MUNIZ |
| Issued | 7/15/2020 | APPLICANT |
| CofO in Progress | 9/10/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
| CofO Issued | 9/29/2021 | DEROLD HAUFF |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 5/12/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 5/14/2020 | EMIL KYUPELYAN |
| ZI | Cleared | 6/8/2020 | MIGUEL GAMBOA |
| Tenant Habitability Plan | Cleared | 6/10/2020 | PHILLIP MUNGUIA |
| Green Code | Cleared | 6/25/2020 | MICHAEL AYERS |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | California Top Remodeling Inc; Lic. No.: 781815-B | 1611 TALMADGE ST #5 LOS ANGELES, CA 90027 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/29/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/2/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Sewer | 10/2/2020 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 10/2/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/15/2020 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 11/12/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 11/12/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/22/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 1/22/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 2/12/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 3/1/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/8/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/8/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/8/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 3/8/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/5/2021 | Partial Approval | DONALD CRICHLOW |
| BUILDING-Rough-Frame | 4/12/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/12/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 4/12/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/12/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/12/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/21/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 4/21/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/28/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/13/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 8/13/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 8/13/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 8/13/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/23/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 8/23/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 8/23/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Final | 8/27/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 9/10/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |