3068 N TYBURN ST 90039

Certificate Information: 3068 N TYBURN ST 90039

Application / Permit
20014-20000-01589
Plan Check / Job No.
B20VN05539
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
13' X 14'-6" ADDITION TO CREATE 2ND-STORY TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT WITH UNCOVERED DECK.
Permit Issued
Issued on 7/15/2020
Issuing Office
Current Status
CofO Issued on 9/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 SERGIO MUNIZ
Corrections Issued 5/6/2020 SERGIO MUNIZ
Quality Review Completed 5/18/2020 OMID HEDAYAT
Building Plans Picked Up 5/22/2020 APPLICANT
Green Plans Picked Up 5/27/2020 APPLICANT
Plan Check Approved 7/14/2020 SERGIO MUNIZ
Issued 7/15/2020 APPLICANT
CofO in Progress 9/10/2021 HAMIK HARTOUNIAN
Permit Finaled 9/29/2021 DEROLD HAUFF
CofO Issued 9/29/2021 DEROLD HAUFF
Permit Finaled 9/29/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/12/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 5/12/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 5/14/2020 EMIL KYUPELYAN
Sewer availability Cleared 5/14/2020 EMIL KYUPELYAN
ZI Cleared 6/8/2020 MIGUEL GAMBOA
Tenant Habitability Plan Cleared 6/10/2020 PHILLIP MUNGUIA
Green Code Cleared 6/25/2020 MICHAEL AYERS

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor California Top Remodeling Inc; Lic. No.: 781815-B 1611 TALMADGE ST #5      LOS ANGELES, CA 90027
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/29/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/2/2020 Partial Approval HAMIK HARTOUNIAN
Sewer 10/2/2020 Approved HAMIK HARTOUNIAN
Underground Mechanical 10/2/2020 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/15/2020 Approved HAMIK HARTOUNIAN
Special/Order Compliance 11/12/2020 Partial Inspection HAMIK HARTOUNIAN
Wood Frame 11/12/2020 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/22/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 1/22/2021 Partial Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/12/2021 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 2/12/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 3/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/8/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 3/8/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 3/8/2021 Conditional Approval HAMIK HARTOUNIAN
Wood Frame 3/8/2021 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/5/2021 Partial Approval DONALD CRICHLOW
BUILDING-Rough-Frame 4/12/2021 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/12/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 4/12/2021 Approved HAMIK HARTOUNIAN
Insulation 4/12/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 4/12/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/21/2021 Conditional Approval HAMIK HARTOUNIAN
Insulation 4/21/2021 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 4/28/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/13/2021 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Final 8/13/2021 Approved CHRIS CHRISTENSEN
Final 8/13/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 8/13/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 8/13/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 8/13/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 8/13/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/23/2021 Approved HAMIK HARTOUNIAN
Final 8/23/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 8/23/2021 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/23/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Final 8/27/2021 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/27/2021 SGSOV Approved HAMIK HARTOUNIAN
Final 9/10/2021 OK to Issue CofO HAMIK HARTOUNIAN