7220 N ALABAMA AVE 91303
Certificate Information: 7220 N ALABAMA AVE 91303
- Application / Permit
- 20014-20000-01565
- Plan Check / Job No.
- B20VN05507
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (8) Auto Repair Garage
- Work Description
- ADD 10' X 22' OFFICE TO EXISTING AUTO REPAIR COMPLY WITH DEPARTMENT ORDER effective date 09/23/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 7/2/2024
- Issuing Office
- Valley
- Current Status
- Issued on 7/2/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/5/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 5/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | JEFFREY TANGONAN |
| Corrections Issued | 5/27/2020 | JEFFREY TANGONAN |
| Quality Review Completed | 5/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/29/2020 | APPLICANT |
| Green Plans Picked Up | 6/4/2020 | APPLICANT |
| Plan Check Approved | 5/30/2024 | SELLA BENYAMIN |
| Issued | 7/2/2024 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 1/7/2021 | JEFFREY TANGONAN |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 11/1/2022 | COLIN LOREDO |
| Work Adjacent to Public Way | Cleared | 11/1/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2022 | COLIN LOREDO |
| Green Code | Cleared | 1/10/2023 | AARON COSTA |
| "Q" conditions | Cleared | 8/8/2023 | NATHAN ROMINE |
| Supp. Use District POD/CDO/TDO | Cleared | 8/8/2023 | JEFFREY TANGONAN |
| ZI | Cleared | 8/8/2023 | JEFFREY TANGONAN |
| Comm Cor/Mini-Mall | Cleared | 12/15/2023 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tabar,, Mehrdad; Lic. No.: C37433 | 14252 CULVER DR A349 IRVINE, CA 92604 |
Inspector Information
| JASON SUMMERS, (818) 374-9837 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIE ROSS, (818) 374-9837 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRYAN MEYER, (818) 374-9837 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL ALEXANDRIAN, (818) 374-9837 | Office Hours: 7:00-8:00 AM MON-FRI |
| JEFFREY DIFIORE, (818) 374-9837 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2024 | Not Ready for Inspection | BEHROUZ HASHEMI |
| Footing/Foundation/Slab | 11/26/2024 | Conditional Approval | BEHROUZ HASHEMI |
| Green Building Rough | 1/3/2025 | Approved | BEHROUZ HASHEMI |
| Wood Frame | 1/3/2025 | Partial Approval | BEHROUZ HASHEMI |
| Wood Frame | 1/14/2025 | Partial Approval | BEHROUZ HASHEMI |
| Wood Frame | 1/23/2025 | Approved | BEHROUZ HASHEMI |
| Final | 2/19/2025 | Not Ready for Inspection | BEHROUZ HASHEMI |
| Footing/Foundation/Slab | 2/19/2025 | Approved | BEHROUZ HASHEMI |
| Green Building Final | 2/19/2025 | Not Ready for Inspection | BEHROUZ HASHEMI |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Not Ready | BEHROUZ HASHEMI |
| Drywall Nailing | 3/11/2025 | Approved | BEHROUZ HASHEMI |
| Final | 11/7/2025 | Conditional Approval | BEHROUZ HASHEMI |
| Green Building Final | 11/7/2025 | Approved | BEHROUZ HASHEMI |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV No Gas | BEHROUZ HASHEMI |
| Final | 3/9/2026 | Conditional Approval | BEHROUZ HASHEMI |