20412 W JUNEAU PL 91364
Certificate Information: 20412 W JUNEAU PL 91364
- Application / Permit
- 20014-20000-01561
- Plan Check / Job No.
- B20VN05499
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) ATTACHED PATIO COVER IN THE REAR OF THE SINGLE FAMILY DWELLING AND ADD 17'-6" x 27'-7" TO THE REAR AND REMODEL (E) BATHROOM, SITTING ROOM, AND MASTER BEDROOM.
- Permit Issued
- Issued on 8/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | SEAN SHAHMIRI |
| Corrections Issued | 5/7/2020 | SEAN SHAHMIRI |
| Green Plans Picked Up | 5/14/2020 | APPLICANT |
| Quality Review Completed | 5/29/2020 | RARES BODEA |
| Building Plans Picked Up | 6/1/2020 | APPLICANT |
| Applicant returned to address corrections | 8/11/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 8/18/2020 | SEAN SHAHMIRI |
| Issued | 8/27/2020 | APPLICANT |
| CofO in Progress | 5/21/2021 | DAVID SANDOVAL |
| CofO Issued | 6/5/2021 | MICHAEL SMITH |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 6/9/2020 | STEVEN WECHSLER |
| Sewer availability | Cleared | 6/19/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 6/23/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 7/10/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 7/24/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/27/2020 | ADRIAN CASTRO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/1/2020 | No Access for Inspection | PAUL CHOPP |
| Footing/Foundation/Slab | 10/2/2020 | Approved | DAVID SCANTLIN |
| Deputy Wood Construction | 10/22/2020 | Approved | PAUL CHOPP |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Approved | PAUL CHOPP |
| Deputy Wood Construction | 10/23/2020 | No Access for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 11/18/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/23/2020 | Approved | TROY SANDERS |
| Insulation | 11/23/2020 | Approved | TROY SANDERS |
| Drywall Nailing | 12/23/2020 | Partial Approval | PAUL CHOPP |
| Green Building Rough | 12/23/2020 | Approved | PAUL CHOPP |
| Drywall Nailing | 12/24/2020 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/24/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 12/24/2020 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 12/30/2020 | Approved | PAUL CHOPP |
| PLUMBING-Rough | 12/30/2020 | Approved | PAUL CHOPP |
| BUILDING-Rough-Frame | 1/12/2021 | Approved | PAUL CHOPP |
| Interior/Exterior Lathing | 1/19/2021 | Approved | PAUL CHOPP |
| ELECTRICAL-Final | 4/13/2021 | Approved | VINCENT HANLEY |
| Final | 4/13/2021 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 4/13/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/13/2021 | Approved | VINCENT HANLEY |
| Final | 5/18/2021 | Partial Inspection | DAVID SANDOVAL |
| Green Building Final | 5/18/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 5/18/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 5/18/2021 | Approved | DAVID SANDOVAL |
| Final | 5/21/2021 | OK to Issue CofO | DAVID SANDOVAL |