1010 S CITRUS AVE 90019

Certificate Information: 1010 S CITRUS AVE 90019

Application / Permit
20014-20000-01552
Plan Check / Job No.
B20VN05464
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DET GARAGE INTO ACCESSORY DWELLING UNIT WITH 8'-5"X5'-10" & 14'4"X9'1" ADDITIONS PER ENGINEER DESIGN.
Permit Issued
Issued on 9/30/2020
Issuing Office
Current Status
Issued on 9/30/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/20/2020 ARTIN ZARUKIAN
Corrections Issued 4/20/2020 ARTIN ZARUKIAN
Building Plans Picked Up 4/28/2020 APPLICANT
Applicant returned to address corrections 7/30/2020 ROSENDO MEDINA
Applicant returned to address corrections 8/19/2020 HAYATO TSUCHIYA
Plan Check Approved 9/3/2020 MOHAMMAD ESMAILI
Issued 9/30/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/9/2020 ELAINE LEI
Roof/Waste drainage to street Cleared 7/9/2020 ELAINE LEI
CPC Cleared 7/10/2020 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 7/10/2020 ELAINE LEI
Sewer availability Cleared 7/10/2020 ELAINE LEI
Construction near power lines Cleared 7/16/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: C83911 121 N VAIL AVE      MONTEBELLO, CA 90640

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/6/2020 Approved ARTHUR SARGSYAN
Deputy Drilled-In Anchors 10/7/2020 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 10/13/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 11/30/2020 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 11/30/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 11/30/2020 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 11/30/2020 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 12/28/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 12/28/2020 Partial Approval SCOTT FINNILA
Green Building Rough 12/28/2020 Corrections Issued SCOTT FINNILA
HVAC-Rough 12/28/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 12/28/2020 Approved SCOTT FINNILA
Green Building Rough 1/8/2021 Approved CHRIS CHRISTENSEN
Insulation 1/22/2021 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 1/22/2021 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 2/4/2021 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 5/25/2021 Approved JOSEPH MCGARRY
Insulation 5/25/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 5/25/2021 Partial Approval JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 5/25/2021 Approved JOSEPH MCGARRY
Drywall Nailing 6/15/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 6/15/2021 Approved THOMAS LOGRASSO
Shower Pan 6/15/2021 Approved THOMAS LOGRASSO
Final 10/25/2021 Not Ready for Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 10/25/2021 Approved ARTHUR SARGSYAN
Green Building Final 10/25/2021 Approved ARTHUR SARGSYAN
METHANE-Barrier 10/25/2021 Approved ARTHUR SARGSYAN
METHANE-Subgrade 10/25/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 10/25/2021 Approved ARTHUR SARGSYAN