5320 N BILOXI AVE 91601
Certificate Information: 5320 N BILOXI AVE 91601
- Application / Permit
- 20014-20000-01551
- Plan Check / Job No.
- B20VN05461
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 22'-9" X 21'-7" IRREGULAR SHAPED ADDITION TO AND CONVERT THE (E) 18'-1" X 20'-1" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER ENGINEERING.
- Permit Issued
- Issued on 7/6/2020
- Issuing Office
- Current Status
- CofO Issued on 8/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 4/21/2020 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 5/18/2020 | JENNIFER LEE |
| Plan Check Approved | 6/15/2020 | LUIS RINCON |
| Issued | 7/6/2020 | APPLICANT |
| CofO in Progress | 8/31/2021 | DANIEL DREW |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
| CofO Issued | 8/24/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2020 | WALLIE JONG |
| Permit | Cleared | 5/4/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2020 | WALLIE JONG |
| Construction near power lines | Cleared | 5/7/2020 | OSCAR CASTRO |
| Roof/Waste drainage to street | Cleared | 5/21/2020 | WALLIE JONG |
| Sewer availability | Cleared | 5/27/2020 | WALLIE JONG |
| Trees in Parkway | Cleared | 6/2/2020 | JOHN KIM |
Contact Information
| Contractor | Your Favorite Contractor Inc; Lic. No.: 851344-B | 18375 VENTURA BLVD #402 TARZANA, CA 91356 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2020 | Approved | RAYMOND KEHOE |
| HVAC-Rough | 7/7/2020 | Approved | RAYMOND KEHOE |
| Underground Mechanical | 7/7/2020 | Approved | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 7/29/2020 | Approved | RAYMOND KEHOE |
| ELECTRICAL-Rough | 7/29/2020 | Approved | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2020 | Approved | RAYMOND KEHOE |
| Green Building Rough | 7/29/2020 | Approved | RAYMOND KEHOE |
| HVAC-Rough | 7/29/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Rough | 7/29/2020 | Approved | RAYMOND KEHOE |
| Insulation | 8/10/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 8/10/2020 | Approved | DANIEL DREW |
| Shower Pan | 8/10/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 8/17/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 9/30/2020 | Corrections Issued | DANIEL DREW |
| Final | 9/30/2020 | Corrections Issued | DANIEL DREW |
| Green Building Final | 9/30/2020 | Corrections Issued | DANIEL DREW |
| HVAC-Final | 9/30/2020 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Final | 9/30/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 9/30/2020 | Approved | DANIEL DREW |
| Green Building Final | 1/27/2021 | Approved | DANIEL DREW |
| HVAC-Final | 1/27/2021 | Approved | DANIEL DREW |
| Final | 8/23/2021 | Not Ready for Inspection | DANIEL DREW |
| Final | 8/30/2021 | OK to Issue CofO | DANIEL DREW |