3858 N HAYVENHURST DR 91436

Certificate Information: 3858 N HAYVENHURST DR 91436

Application / Permit
20014-20000-01550
Plan Check / Job No.
B20VN05458
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, REMOVE REPLACE DECK AT FRONT ENTRANCE, REMOVE BEARING WALL IN DINING AREA, REMOVE PORTION OF ROOF LIVING ROOM AREA ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/14/2021
Issuing Office
Current Status
Permit Finaled on 2/19/2025

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/12/2020 SEWADA ZADOORIAN MILAGARDI
Green Plans Picked Up 5/12/2020 APPLICANT
Quality Review Completed 5/13/2020 OMID HEDAYAT
Building Plans Picked Up 5/19/2020 APPLICANT
Applicant returned to address corrections 6/5/2020 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/11/2020 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 6/29/2020 SEWADA ZADOORAN MILAGARDI
Issued 1/14/2021 APPLICANT
Permit Finaled 11/7/2024 THOMAS FINNILA
CofO in Progress 11/8/2024 THOMAS FINNILA
CofO in Progress 2/19/2025 THOMAS FINNILA

Permit Application Clearance Information

Green Code Cleared 6/3/2020 AARON COSTA
Grading Pre-Inspection Cleared 6/9/2020 TIMOTHY POWELL
Eng Process Fee Ord 176,300 Cleared 6/11/2020 JOHN LIN
Roof/Waste drainage to street Cleared 6/11/2020 JOHN LIN
Miscellaneous Cleared 6/17/2020 LAUREN PADICK
Miscellaneous Cleared 6/17/2020 LAUREN PADICK
ZI Cleared 6/17/2020 LAUREN PADICK

Contact Information

Contractor G H B W; Lic. No.: 983577-B 3209 LA CIENAGA AVE      LOS ANGELES, CA 90034
Engineer Moon,, Samuel Sukjoon; Lic. No.: C49445 2875 MARICOPA ST      TORRANCE, CA 90503

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/30/2021 Not Ready for Inspection RONALD COWAN
Green Building Rough 4/30/2021 Not Ready for Inspection RONALD COWAN
Insulation 7/26/2021 Approved RONALD COWAN
Drywall Nailing 9/21/2021 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 9/28/2021 Approved RONALD COWAN
HVAC-Rough 9/28/2021 Approved RONALD COWAN
Interior/Exterior Lathing 9/28/2021 Approved RONALD COWAN
PLUMBING-Rough 9/28/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 7/7/2022 Approved VINCENT HANLEY
Final 7/7/2022 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 7/7/2022 Approved VINCENT HANLEY
Green Building Final 7/7/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 7/7/2022 Approved VINCENT HANLEY
Final 8/17/2022 Partial Inspection VINCENT HANLEY
Final 10/23/2024 Corrections Issued THOMAS FINNILA
Final 11/7/2024 Permit Finaled THOMAS FINNILA