- ADDITION OF 19'-4 1/2" x 19'-1/2" (IRREGULAR SHAPE) TO (E) SINGLE FAMILY DWELLING TO ADD A NEW MASTER BEDROOM AND MAJOR REMODEL TO SFD AND NEW ROOF/FACADE AT (E) FRONT PORCH AND PORTION OF (E) LIVING ROOM. COMPLY WITH DEPARTMENT ORDER effective date 05/13/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 6/25/2020
- Issuing Office
- Current Status
- CofO Issued on 3/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | SEAN SHAHMIRI |
| Corrections Issued | 4/27/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 5/11/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 5/12/2020 | APPLICANT |
| Green Plans Picked Up | 5/12/2020 | APPLICANT |
| Plan Check Approved | 6/25/2020 | SEAN SHAHMIRI |
| Issued | 6/25/2020 | APPLICANT |
| CofO in Progress | 3/17/2022 | JOEL WILLIAMS |
| Permit Finaled | 3/22/2022 | DANIEL SANCHEZ |
| CofO Issued | 3/22/2022 | DANIEL SANCHEZ |
| Permit Finaled | 3/22/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2020 | RENZ SORIANO |
| Low Impact Development | Cleared | 6/11/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/15/2020 | RENZ SORIANO |
| Green Code | Cleared | 6/16/2020 | MICHAEL AYERS |
| Sewer availability | Cleared | 6/24/2020 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 8/13/2020 | Partial Inspection | GORDON ZUBER |
| Rough-Elec/Plmb/HVAC | 10/21/2020 | Corrections Issued | EDDY ARDESSI |
| ELECTRICAL-Rough | 10/26/2020 | Not Ready for Inspection | EDDY ARDESSI |
| PLUMBING-Rough | 10/26/2020 | Approved | EDDY ARDESSI |
| ELECTRICAL-Final | 4/28/2021 | Corrections Issued | JOEL WILLIAMS |
| Final | 4/28/2021 | Corrections Issued | JOEL WILLIAMS |
| HVAC-Final | 4/28/2021 | Corrections Issued | JOEL WILLIAMS |
| PLUMBING-Final | 4/28/2021 | Corrections Issued | JOEL WILLIAMS |
| Smoke Detectors | 4/28/2021 | Approved | JOEL WILLIAMS |
| BUILDING-Rough-Frame | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| Drywall Nailing | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| Final | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| Footing/Foundation/Slab | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| Green Building Final | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| Green Building Rough | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| METHANE-Barrier | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| METHANE-Final | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| METHANE-Rough | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| METHANE-Subgrade | 6/25/2021 | Not Ready for Inspection | GORDON ZUBER |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Not Ready | GORDON ZUBER |
| BUILDING-Rough-Frame | 8/9/2021 | Not Ready for Inspection | ZEYDI STEWART |
| Drywall Nailing | 8/9/2021 | Approved | ZEYDI STEWART |
| Final | 8/9/2021 | Not Ready for Inspection | ZEYDI STEWART |
| Footing/Foundation/Slab | 8/9/2021 | Not Ready for Inspection | ZEYDI STEWART |
| Green Building Final | 8/9/2021 | Approved | ZEYDI STEWART |
| Green Building Rough | 8/9/2021 | Approved | ZEYDI STEWART |
| METHANE-Barrier | 8/9/2021 | Not Ready for Inspection | ZEYDI STEWART |
| METHANE-Final | 8/9/2021 | Not Ready for Inspection | ZEYDI STEWART |
| METHANE-Rough | 8/9/2021 | Not Ready for Inspection | ZEYDI STEWART |
| METHANE-Subgrade | 8/9/2021 | Not Ready for Inspection | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Approved | ZEYDI STEWART |
| BUILDING-Rough-Frame | 8/10/2021 | Approved | JOEL WILLIAMS |
| Final | 8/10/2021 | Corrections Issued | JOEL WILLIAMS |
| Footing/Foundation/Slab | 8/10/2021 | Approved | JOEL WILLIAMS |
| METHANE-Barrier | 8/10/2021 | Approved | JOEL WILLIAMS |
| METHANE-Final | 8/10/2021 | Approved | JOEL WILLIAMS |
| METHANE-Rough | 8/10/2021 | Approved | JOEL WILLIAMS |
| METHANE-Subgrade | 8/10/2021 | Approved | JOEL WILLIAMS |
| Final | 3/17/2022 | OK to Issue CofO | JOEL WILLIAMS |
| Service/Power Release | 3/17/2022 | Approved | JOEL WILLIAMS |