7511 N LASAINE AVE 91406
Certificate Information: 7511 N LASAINE AVE 91406
- Application / Permit
- 20014-20000-01544
- Plan Check / Job No.
- B20VN05443
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATT. 1-CAR GARAGE INTO MASTER BEDROOM/BATH/CLOSET. AND NEW ATT. 1-CAR CARPORT PER INFO BULLETIN, P/BC 2020-005. CLOSE-UP EXISTING EXTERIOR OPENINGS PER PLAN. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Current Status
- CofO Issued on 1/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 4/20/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 6/3/2020 | RAPHAEL ROSAS |
| Issued | 6/3/2020 | APPLICANT |
| CofO in Progress | 12/14/2020 | ARTHUR SARGSYAN |
| CofO in Progress | 12/14/2020 | ARTHUR SARGSYAN |
| Permit Finaled | 1/2/2021 | MICHAEL SMITH |
| CofO Issued | 1/2/2021 | MICHAEL SMITH |
| Permit Finaled | 1/2/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 5/11/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 5/11/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/15/2020 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 6/15/2020 | Partial Approval | MICHEL ABAJAN |
| Sewer | 6/15/2020 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/17/2020 | Approved | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 7/7/2020 | Not Ready for Inspection | ROBERT MINASSIANS |
| Rough-Elec/Plmb/HVAC | 7/10/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 7/13/2020 | Corrections Issued | DANIEL DREW |
| Green Building Rough | 7/13/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 7/13/2020 | Approved | DANIEL DREW |
| Deputy Drilled-In Anchors | 7/15/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 7/16/2020 | Approved | DANIEL DREW |
| Insulation | 7/16/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 7/22/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 7/22/2020 | Approved | DANIEL DREW |
| Final | 8/21/2020 | Corrections Issued | DANIEL ORRANTE |
| Green Building Final | 8/21/2020 | Corrections Issued | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Approved | DANIEL ORRANTE |
| Smoke Detectors | 8/21/2020 | Corrections Issued | DANIEL ORRANTE |
| Final | 8/26/2020 | Partial Inspection | DANIEL ORRANTE |
| Green Building Final | 8/26/2020 | Approved | DANIEL ORRANTE |
| Smoke Detectors | 8/26/2020 | Approved | DANIEL ORRANTE |
| Final | 11/10/2020 | Corrections Issued | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 11/18/2020 | Approved | MICHAEL TEMPLE |
| Final | 11/18/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 12/9/2020 | OK to Issue CofO | ARTHUR SARGSYAN |