5327 N TEESDALE AVE 91607
Certificate Information: 5327 N TEESDALE AVE 91607
- Application / Permit
- 20014-20000-01542
- Plan Check / Job No.
- B20VN05439
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 4/10/2021
- Issuing Office
- Current Status
- CofO Issued on 12/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/7/2020 | MOHAMMAD ESMAILI |
| Green Plans Picked Up | 5/7/2020 | APPLICANT |
| Quality Review Completed | 5/18/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 5/26/2020 | APPLICANT |
| Plan Check Approved | 11/9/2020 | MOHAMMAD ESMAILI |
| Issued | 4/10/2021 | APPLICANT |
| CofO in Progress | 12/10/2021 | CHRISTOPHE COCHRAN |
| CofO in Progress | 12/10/2021 | CHRISTOPHE COCHRAN |
| Permit Finaled | 12/30/2021 | MICHAEL SMITH |
| CofO Issued | 12/30/2021 | MICHAEL SMITH |
| Permit Finaled | 12/30/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/28/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 6/4/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 7/21/2020 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 10/2/2020 | AARON COSTA |
| Specific Plan | Cleared | 10/15/2020 | MARIANNE KING |
| ZI | Cleared | 10/15/2020 | MARIANNE KING |
| Roof/Waste drainage to street | Cleared | 10/16/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | S E S Builders Inc; Lic. No.: 1030945-B | 15643 SHERMAN WAY #120 VAN NUYS, CA 91406 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/12/2021 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 5/20/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 6/21/2021 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 6/21/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 6/21/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 6/22/2021 | Approved | RICHARD DOCKUS |
| Gas Test | 6/22/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 6/22/2021 | Approved | RICHARD DOCKUS |
| Gas Test | 6/23/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 8/3/2021 | Approved | CHARLES POWELL |
| Green Building Rough | 8/3/2021 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Rough | 8/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 8/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/9/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Drywall Nailing | 8/13/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 12/1/2021 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 12/1/2021 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2021 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/1/2021 | Approved | CHRISTOPHE COCHRAN |