4318 N KLUMP AVE 91602
Certificate Information: 4318 N KLUMP AVE 91602
- Application / Permit
- 20014-20000-01532
- Plan Check / Job No.
- B20VN05420
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-3" X 18'-6" DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT AND 20' X 14'-9" ADDITION PER LAMC 12.22 A.33(c) and (d). SEE COMMENTS FOR ACTIVE PERMITS.
- Permit Issued
- Issued on 10/13/2020
- Issuing Office
- Current Status
- CofO Issued on 1/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 9/9/2020 | OMAR GARNICA |
| Issued | 10/13/2020 | APPLICANT |
| CofO in Progress | 12/13/2022 | JOHN COLEMAN |
| CofO Issued | 1/24/2023 | MICHAEL SMITH |
| Permit Finaled | 1/24/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 5/5/2020 | STEVEN WECHSLER |
| Address approval | Cleared | 5/6/2020 | CECILIO NAVARRO |
| Tract Map conditions | Cleared | 5/7/2020 | VINCENT QUITORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 5/12/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 8/14/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/20/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Steele Builders Inc; Lic. No.: 1037702-B | 23100 COLLINS STREET WOODLAND HILLS, CA 91367 |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/19/2020 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/23/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/29/2020 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/9/2020 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 1/4/2021 | Corrections Issued | THOMAS FINNILA |
| Sewer | 1/4/2021 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 1/4/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2021 | Conditional Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 1/6/2021 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/12/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 1/12/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/14/2021 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 1/14/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/14/2021 | Partial Approval | THOMAS FINNILA |
| MERV13>=Rough | 1/14/2021 | Approved | THOMAS FINNILA |
| Shower Pan | 1/14/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/19/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 1/19/2021 | Approved | THOMAS FINNILA |
| Insulation | 1/19/2021 | Conditional Approval | THOMAS FINNILA |
| Shower Pan | 1/19/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Drywall Nailing | 1/22/2021 | Approved | THOMAS FINNILA |
| Insulation | 1/22/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 5/14/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 5/14/2021 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 5/14/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 5/14/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| MERV13>=Final | 3/21/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Not Ready | THOMAS FINNILA |
| ELECTRICAL-Final | 8/25/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 8/25/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 8/25/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 9/6/2022 | Corrections Issued | DAVID ANDERSON |
| HVAC-Final | 9/6/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 9/6/2022 | Approved | DAVID ANDERSON |
| Service/Power Release | 9/6/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 9/23/2022 | Approved | THOMAS FINNILA |
| Final | 9/23/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 9/23/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 9/23/2022 | Approved | THOMAS FINNILA |
| Final | 11/1/2022 | Conditional Approval | JACK KARGODORIAN |
| Final | 12/13/2022 | OK to Issue CofO | JOHN COLEMAN |