6319 N WHITSETT AVE 91606

Certificate Information: 6319 N WHITSETT AVE 91606

Application / Permit
20014-20000-01529
Plan Check / Job No.
B20VN05414
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT & EXTEND (IRR 42'-6" X 20'-5") PER LAMC 12.22A33(c)(d) [The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy]
Permit Issued
Issued on 7/22/2022
Issuing Office
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 NILOOFAR MEHRAIN
Corrections Issued 5/7/2020 NILOOFAR MEHRAIN
Quality Review Completed 5/7/2020 STEVEN KIM
Building Plans Picked Up 5/13/2020 APPLICANT
Green Plans Picked Up 7/9/2020 APPLICANT
Applicant returned to address corrections 6/15/2022 NILOOFAR MEHRAIN
Plan Check Approved 7/14/2022 NILOOFAR MEHRAIN
Issued 7/22/2022 APPLICANT
CofO in Progress 6/24/2024 JOSE AVILA
Permit Finaled 7/10/2024 RUBEN SALAS
CofO Issued 7/10/2024 RUBEN SALAS
Permit Finaled 7/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/24/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/24/2022 CARLOS AGUILERA
Permit Cleared 2/24/2022 CARLOS AGUILERA
Sewer availability Cleared 2/24/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 4/11/2022 LAURINDA MEADE
Green Code Cleared 6/15/2022 MICHAEL AYERS
Roof/Waste drainage to street Cleared 7/14/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2023 Approved KIRK SANDERS
Underground Mechanical 4/18/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 5/3/2023 Partial Approval JOHN COLEMAN
Green Building Rough 5/3/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 5/3/2023 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval KIRK SANDERS
Green Building Rough 5/23/2023 Not Ready for Inspection KIRK SANDERS
Insulation 5/23/2023 Partial Approval KIRK SANDERS
Deputy Drilled-In Anchors 7/7/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 7/13/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Partial Approval KIRK SANDERS
PLUMBING-Rough 7/13/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 7/25/2023 Approved KIRK SANDERS
Underground Mechanical 7/25/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 7/28/2023 Approved KIRK SANDERS
Green Building Rough 7/28/2023 Approved KIRK SANDERS
HVAC-Rough 7/28/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 8/3/2023 Partial Approval KIRK SANDERS
Insulation 8/14/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 No Access for Inspection KIRK SANDERS
Drywall Nailing 8/31/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Approved KIRK SANDERS
Final 3/22/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 3/22/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 3/22/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/22/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 4/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/2/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/2/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/2/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 4/5/2024 Corrections Issued JOSE AVILA
Gas Test 5/21/2024 Approved OGANES TARAKHCHYAN
Final 6/24/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 6/24/2024 Approved JOSE AVILA