3033 S 4TH AVE 90018
Certificate Information: 3033 S 4TH AVE 90018
- Application / Permit
- 20014-20000-01499
- Plan Check / Job No.
- B20VN05316
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 28'-10" X 20'THREE GARAGE AND (E) 22' X 19'-1"SECOND STORY SINGLE FAMILY DWELLING TO A TWO STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- CofO Issued on 11/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | SEWADA ZADOORIAN MILAGARDI |
| Green Plans Picked Up | 4/30/2020 | APPLICANT |
| Corrections Issued | 5/5/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 5/18/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 11/8/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 12/27/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 3/23/2022 | APPLICANT |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| CofO in Progress | 10/30/2023 | CALEB MEISTER |
| CofO Issued | 11/2/2023 | DEROLD HAUFF |
| Permit Finaled | 11/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2020 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/18/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 6/18/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2020 | ELENA LOPEZ |
| Green Code | Cleared | 9/17/2020 | DAVID MATSON |
| HPOZ | Cleared | 5/6/2021 | MAX LODER |
| Historic monument | Cleared | 5/6/2021 | MAX LODER |
| ZI | Cleared | 5/6/2021 | MAX LODER |
| ZI | Cleared | 5/6/2021 | MAX LODER |
| Tenant Habitability Plan | Cleared | 5/14/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Busy Bee Construction Solution Inc; Lic. No.: 1029800-B | 92 CORPORATE PRK STE C IRVINE, CA 92606 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/27/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 4/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 4/27/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/9/2022 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/9/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 5/9/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 5/9/2022 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/9/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 5/9/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 5/9/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/13/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/13/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 5/13/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 5/18/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 5/26/2022 | Conditional Approval | STUART CHAPMAN |
| Green Building Rough | 5/26/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/17/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/17/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 8/29/2022 | Approved | STUART CHAPMAN |
| Final | 8/29/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/29/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/29/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 8/29/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 9/8/2022 | Corrections Issued | STUART CHAPMAN |
| Smoke Detectors | 9/8/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 9/26/2022 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 9/26/2022 | Corrections Issued | JOSE AVILA |
| Final | 10/1/2022 | Corrections Issued | ASHLEY THOMPSON |
| Smoke Detectors | 10/1/2022 | Approved | ASHLEY THOMPSON |
| Final | 10/30/2023 | OK to Issue CofO | CALEB MEISTER |