3033 S 4TH AVE 90018

Certificate Information: 3033 S 4TH AVE 90018

Application / Permit
20014-20000-01499
Plan Check / Job No.
B20VN05316
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 28'-10" X 20'THREE GARAGE AND (E) 22' X 19'-1"SECOND STORY SINGLE FAMILY DWELLING TO A TWO STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/23/2022
Issuing Office
Current Status
CofO Issued on 11/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2020 APPLICANT
Assigned to Plan Check Engineer 4/23/2020 SEWADA ZADOORIAN MILAGARDI
Green Plans Picked Up 4/30/2020 APPLICANT
Corrections Issued 5/5/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/18/2020 OMID HEDAYAT
Applicant returned to address corrections 11/8/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 12/27/2021 SEWADA ZADOORAN MILAGARDI
Issued 3/23/2022 APPLICANT
Building Plans Picked Up 3/30/2022 APPLICANT
CofO in Progress 10/30/2023 CALEB MEISTER
CofO Issued 11/2/2023 DEROLD HAUFF
Permit Finaled 11/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/18/2020 ELENA LOPEZ
Roof/Waste drainage to street Cleared 6/18/2020 ELENA LOPEZ
Sewer availability Cleared 6/18/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/19/2020 ELENA LOPEZ
Green Code Cleared 9/17/2020 DAVID MATSON
HPOZ Cleared 5/6/2021 MAX LODER
Historic monument Cleared 5/6/2021 MAX LODER
ZI Cleared 5/6/2021 MAX LODER
ZI Cleared 5/6/2021 MAX LODER
Tenant Habitability Plan Cleared 5/14/2021 ISMAEL HERNANDEZ

Contact Information

Contractor Busy Bee Construction Solution Inc; Lic. No.: 1029800-B 92 CORPORATE PRK STE C      IRVINE, CA 92606

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/31/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 4/27/2022 Corrections Issued STUART CHAPMAN
Green Building Rough 4/27/2022 Not Ready for Inspection STUART CHAPMAN
Rough-Elec/Plmb/HVAC 4/27/2022 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 5/9/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 5/9/2022 Approved STUART CHAPMAN
Green Building Rough 5/9/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 5/9/2022 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 5/9/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 5/9/2022 Approved STUART CHAPMAN
Shower Pan 5/9/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/13/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 5/13/2022 Approved STUART CHAPMAN
Green Building Rough 5/13/2022 Not Ready for Inspection STUART CHAPMAN
Insulation 5/18/2022 Approved STUART CHAPMAN
Drywall Nailing 5/26/2022 Conditional Approval STUART CHAPMAN
Green Building Rough 5/26/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 6/17/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/17/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/29/2022 Approved STUART CHAPMAN
Drywall Nailing 8/29/2022 Approved STUART CHAPMAN
Final 8/29/2022 Corrections Issued STUART CHAPMAN
Green Building Final 8/29/2022 Approved STUART CHAPMAN
Green Building Rough 8/29/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/29/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 8/29/2022 Not Ready for Inspection STUART CHAPMAN
Final 9/8/2022 Corrections Issued STUART CHAPMAN
Smoke Detectors 9/8/2022 Not Ready for Inspection STUART CHAPMAN
Final 9/26/2022 Corrections Issued JOSE AVILA
Smoke Detectors 9/26/2022 Corrections Issued JOSE AVILA
Final 10/1/2022 Corrections Issued ASHLEY THOMPSON
Smoke Detectors 10/1/2022 Approved ASHLEY THOMPSON
Final 10/30/2023 OK to Issue CofO CALEB MEISTER