7300 S DUNFIELD AVE 90045
Certificate Information: 7300 S DUNFIELD AVE 90045
- Application / Permit
- 20014-20000-01496
- Plan Check / Job No.
- B20VN05313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 6'-6" X 13'-11" & 31' X 26' IRREGULAR SHAPE ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 7/28/2020
- Issuing Office
- Current Status
- CofO Issued on 12/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | SERGIO MUNIZ |
| Corrections Issued | 4/21/2020 | SERGIO MUNIZ |
| Green Plans Picked Up | 4/23/2020 | APPLICANT |
| Quality Review Completed | 5/4/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 5/8/2020 | APPLICANT |
| Applicant returned to address corrections | 5/29/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/12/2020 | SERGIO MUNIZ |
| Plan Check Approved | 7/14/2020 | SERGIO MUNIZ |
| Issued | 7/28/2020 | APPLICANT |
| CofO in Progress | 11/21/2020 | JUAN VALENZUELA |
| Permit Finaled | 12/10/2020 | VINCENT COTTON |
| CofO Issued | 12/10/2020 | VINCENT COTTON |
| Permit Finaled | 12/10/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/21/2020 | KIRK LINKLATER |
| Green Code | Cleared | 5/19/2020 | DAVID MATSON |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/21/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 6/3/2020 | GABRIEL ROBLES |
| Specific Plan | Cleared | 6/23/2020 | FREDDY GARCIA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/4/2020 | Approved | JOHNNY MIRANDA |
| METHANE-Barrier | 8/4/2020 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 8/4/2020 | Approved | JOHNNY MIRANDA |
| Pre-Inspection | 8/12/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2020 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2020 | Partial Approval | CRAIG DAVIS |
| PLUMBING-Rough | 9/3/2020 | Approved | JOHNNY MIRANDA |
| Shower Pan | 9/8/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/11/2020 | Order to Comply Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/17/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 9/17/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/18/2020 | Partial Approval | JOHNNY MIRANDA |
| Gas Test | 9/18/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/18/2020 | Approved | JOHNNY MIRANDA |
| METHANE-Rough | 9/18/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/25/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/25/2020 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 9/30/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 10/5/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 10/27/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 10/27/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 10/28/2020 | Approved | JOHNNY MIRANDA |
| Final | 11/16/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 11/16/2020 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 11/16/2020 | Approved | JOHNNY MIRANDA |
| Final | 11/20/2020 | OK to Issue CofO | JUAN VALENZUELA |