17522 W OSBORNE ST 91325

Certificate Information: 17522 W OSBORNE ST 91325

Application / Permit
20014-20000-01441
Plan Check / Job No.
B20VN05186
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (89'-6"x 17'-6") MASTER BED & BATHROOM/ WALK-IN CLOSET, 3- BEDROOMS, AND (12'-6"x 37'-7") COV ENTRY PORCH AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH 2-CAR GARAGE. WORK PER ENGINEER.
Permit Issued
Issued on 8/7/2020
Issuing Office
Current Status
Issued on 8/7/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 TROY DEGUZMAN
Corrections Issued 5/7/2020 TROY DEGUZMAN
Quality Review Completed 5/11/2020 CHON CHIO KUO
Building Plans Picked Up 5/13/2020 APPLICANT
Green Plans Picked Up 5/15/2020 APPLICANT
Plan Check Approved 8/6/2020 TROY DEGUZMAN
Issued 8/7/2020 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/15/2020 GUILLERMO PETRA
Sewer availability Cleared 5/15/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 6/1/2020 KURT CORRAL
Green Code Cleared 6/18/2020 MICHAEL AYERS
Low Impact Development Cleared 7/21/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 7/22/2020 ADRIAN CASTRO

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/22/2020 No Access for Inspection MARK JOHNSON
Footing/Foundation/Slab 9/29/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Corrections Issued MARK JOHNSON
PLUMBING-Rough 10/22/2020 Approved MARK JOHNSON
PLUMBING-Rough 11/6/2020 Partial Approval MARK JOHNSON
Wood Frame 1/5/2021 Partial Approval MARK JOHNSON
Deputy Wood Construction 1/6/2021 No Access for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Approved DANIEL ORRANTE
ELECTRICAL-Rough 3/15/2021 Approved MARK JOHNSON
HVAC-Rough 3/15/2021 Corrections Issued MARK JOHNSON
PLUMBING-Rough 3/15/2021 Approved MARK JOHNSON
HVAC-Rough 3/17/2021 Not Ready for Inspection MARK JOHNSON
Wood Frame 3/17/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 4/9/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 4/9/2021 Approved MARK JOHNSON
Wood Frame 4/15/2021 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 4/23/2021 No Access for Inspection SEAN WIRCH
Green Building Rough 4/23/2021 No Access for Inspection SEAN WIRCH
BUILDING-Rough-Frame 5/5/2021 Approved MARK JOHNSON
Green Building Rough 5/5/2021 Approved MARK JOHNSON
Insulation 5/14/2021 Approved KRISTEN CAUSEY
Pre-Inspection 5/14/2021 Partial Inspection JAVIER RAMOS JR
Drywall Nailing 6/1/2021 Approved LILIANA PORTILLO
Shower Pan 7/12/2021 Corrections Issued MICHAEL TEMPLE
Shower Pan 8/2/2021 Corrections Issued AMY COLIN
Interior/Exterior Lathing 8/6/2021 Approved JENNIFER RABUCHIN
Shower Pan 8/6/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/20/2021 Not Ready for Inspection RAUL OLAGI
Gas Test 1/10/2022 Corrections Issued JESUS RODRIGUEZ
Gas Test 1/13/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/13/2022 Corrections Issued JAVIER RAMOS JR
HVAC-Final 6/13/2022 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 6/13/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 6/15/2022 Approved JAVIER RAMOS JR
HVAC-Final 6/15/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 6/15/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 8/16/2022 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Approved DEANDRE HOFFMAN