7408 N KRAFT AVE 91605
Certificate Information: 7408 N KRAFT AVE 91605
- Application / Permit
- 20014-20000-01440
- Plan Check / Job No.
- B20VN05185
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 6'-7.5" X 14'-4.5" ATTACHED PATIO TO LAUNDRY ROOM AND ADD NEW 14'-4.5" X 14'-2" PATIO COVER. ALL WORKS ARE PER DESIGN
- Permit Issued
- Issued on 6/10/2020
- Issuing Office
- Current Status
- CofO Issued on 10/24/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | ALDO UBAU |
| Corrections Issued | 5/14/2020 | ALDO UBAU |
| Plan Check Approved | 5/14/2020 | RAPHAEL ROSAS |
| Issued | 6/10/2020 | APPLICANT |
| CofO in Progress | 9/30/2020 | DANIEL DREW |
| CofO Issued | 10/24/2020 | MICHAEL SMITH |
| Permit Finaled | 10/24/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/5/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Arch Design & Construction; Lic. No.: 791412-B | 730 E OLIVE AVE BURBANK, CA 91501 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/16/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Rough | 7/1/2020 | Approved | RAYMOND KEHOE |
| Sewer | 7/1/2020 | Approved | RAYMOND KEHOE |
| Underground Mechanical | 7/1/2020 | Approved | RAYMOND KEHOE |
| Sewer | 7/2/2020 | Approved | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 7/21/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/21/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/21/2020 | Approved | MATTHEW NELSON |
| Insulation | 7/27/2020 | No Access for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 7/27/2020 | No Access for Inspection | THOMAS FINNILA |
| Insulation | 7/28/2020 | Approved | RAYMOND KEHOE |
| Interior/Exterior Lathing | 7/28/2020 | Partial Approval | RAYMOND KEHOE |
| Drywall Nailing | 8/3/2020 | Approved | DANIEL DREW |
| Final | 9/11/2020 | Corrections Issued | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 9/11/2020 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 9/11/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 9/17/2020 | Approved | DANIEL DREW |
| HVAC-Final | 9/17/2020 | Approved | DANIEL DREW |
| PLUMBING-Final | 9/17/2020 | Approved | DANIEL DREW |
| Final | 9/30/2020 | OK to Issue CofO | DANIEL DREW |