19552 W SUPERIOR ST 91324
Certificate Information: 19552 W SUPERIOR ST 91324
- Application / Permit
- 20014-20000-01431
- Plan Check / Job No.
- B20VN05151
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 12'-0" X 55'-1" TO EXTEND (E) BEDROOMS, ADD 11'-10" X 4'-8" TO THE FRONT, AND REMODEL (E) SFD THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Issued on 7/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 8/19/2020 | ROSENDO MEDINA |
| Issued | 8/19/2020 | APPLICANT |
| CofO in Progress | 7/28/2021 | JEFFREY PARD |
| CofO Issued | 7/28/2021 | JOHN JANSON |
| Permit Finaled | 7/28/2021 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 6/10/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 6/19/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C91162 | 122 N. GRAMERCY PL. LOS ANGELES, CA 90004 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/24/2020 | Not Ready for Inspection | JEFFREY PARD |
| Underground Mechanical | 12/24/2020 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 12/30/2020 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2021 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 2/2/2021 | Approved | JEFFREY PARD |
| HVAC-Rough | 2/2/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/2/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/11/2021 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/11/2021 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 2/11/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/22/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 2/22/2021 | Approved | JEFFREY PARD |
| Insulation | 2/22/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 2/22/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 3/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 3/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 7/2/2021 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 7/2/2021 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 7/2/2021 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 7/2/2021 | Approved | JEFFREY PARD |