592 W SAWYER ST 90034

Certificate Information: 592 W SAWYER ST 90034

Application / Permit
20014-20000-01410
Plan Check / Job No.
B20VN05108
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE ALL EXTERIOR AND INTERIOR WALLS OF EXISTING ONE STORY GARAGE EXCEPT FOR 5 L.F. AT SOUTH SIDE AND 3.5 LF AND 2.5 LF AT EAST SIDE AND BUILD TWO STORY IRREGULAR SHAPED 28'-4" X 19'-6" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/13/2021
Issuing Office
Valley
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/5/2020 SEWADA ZADOORIAN MILAGARDI
Green Plans Picked Up 5/12/2020 APPLICANT
Quality Review Completed 5/21/2020 OMID HEDAYAT
Building Plans Picked Up 5/22/2020 APPLICANT
Plan Check Approved 2/8/2021 SEWADA ZADOORAN MILAGARDI
Issued 5/13/2021 APPLICANT
CofO in Progress 1/26/2024 STUART CHAPMAN
No Progress 2/14/2024 SCOTT FINNILA
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Green Code Cleared 6/25/2020 SEWADA ZADOORAN MILAGARDI
Address approval Cleared 9/10/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/10/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 9/10/2020 RENZ SORIANO
Construction near power lines Cleared 9/14/2020 RIDWAN HARDY
Sewer availability Cleared 9/18/2020 RENZ SORIANO
Permit Cleared 9/21/2020 RENZ SORIANO
Hydrant and Access approval Cleared 10/2/2020 MATTHEW CRAIG
Trees in Parkway Cleared 1/11/2021 JOHN KIM
Zoning Information File Cleared 1/25/2021 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Makeover Builders Inc; Lic. No.: 986740-B 21781 VENTURA BLVD UNIT 634      WOODLAND HILLS, CA 91364
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 5/25/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 5/25/2021 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/26/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2021 Partial Approval STUART CHAPMAN
Deputy Wood Construction 6/11/2021 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 7/13/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/13/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 8/2/2021 Approved DAVID FEILER
Gas Test 8/2/2021 Partial Inspection DAVID FEILER
HVAC-Rough 8/2/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 8/2/2021 Approved DAVID FEILER
Pre-Inspection 8/2/2021 Partial Inspection CALEB MEISTER
HVAC-Rough 8/31/2021 Approved JOAQUIN GREENOUGH
Green Building Rough 9/2/2021 No Access for Inspection FREDDIE RIVERA
Wood Frame 9/2/2021 No Access for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/13/2021 Approved STUART CHAPMAN
Green Building Rough 9/13/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/13/2021 Partial Approval STUART CHAPMAN
Insulation 9/20/2021 Approved STUART CHAPMAN
Drywall Nailing 9/24/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 9/27/2021 Conditional Approval CALEB MEISTER
ELECTRICAL-Final 7/29/2022 Approved STUART CHAPMAN
Final 7/29/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 7/29/2022 Approved STUART CHAPMAN
Green Building Final 7/29/2022 Approved STUART CHAPMAN
HVAC-Final 7/29/2022 Approved STUART CHAPMAN
PLUMBING-Final 7/29/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 7/29/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 1/25/2024 Approved STUART CHAPMAN
Final 1/25/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 1/25/2024 Approved STUART CHAPMAN
PLUMBING-Final 1/25/2024 Approved STUART CHAPMAN
Service/Power Release 1/25/2024 Approved STUART CHAPMAN
Service/Power Release 7/29/2024 Approved STUART CHAPMAN