1901 W 91ST ST 90047
Certificate Information: 1901 W 91ST ST 90047
- Application / Permit
- 20014-20000-01403
- Plan Check / Job No.
- B20VN05092
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 9'-0" X 18'-0" PORTION OF (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT AND ADD 11'-0" X 22'-8". ADD 18'-0" X 4'-8" STORAGE ROOM TO (E) GARAGE PORTION TO REMAIN.
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Issued on 9/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 4/20/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/4/2020 | LUIS RINCON |
| Applicant returned to address corrections | 5/7/2020 | LUIS RINCON |
| Applicant returned to address corrections | 5/14/2020 | LUIS RINCON |
| Applicant returned to address corrections | 7/10/2020 | ALDO UBAU |
| Plan Check Approved | 8/3/2020 | JEROME MAGAT PALMA |
| Issued | 8/19/2020 | APPLICANT |
| CofO in Progress | 9/23/2021 | FREDDIE RIVERA |
| Permit Finaled | 9/27/2021 | DEROLD HAUFF |
| CofO Issued | 9/27/2021 | DEROLD HAUFF |
| Permit Finaled | 9/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 5/8/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 5/11/2020 | JUAN ASHTON |
Contact Information
| Contractor | Foundation To Roof Inc; Lic. No.: 767761-B | 10800 SOUTH LA CIENEGA BL INGLEWOOD, CA 90304 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/24/2020 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 9/24/2020 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/14/2020 | Conditional Approval | FREDDIE RIVERA |
| METHANE-Barrier | 10/14/2020 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 10/14/2020 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 10/14/2020 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/22/2020 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/14/2020 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 12/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 12/14/2020 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 12/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 1/12/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 1/12/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 1/12/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 1/12/2021 | Approved | FREDDIE RIVERA |
| Wood Frame | 1/12/2021 | Approved | FREDDIE RIVERA |
| Insulation | 1/21/2021 | Approved | FREDDIE RIVERA |
| Shower Pan | 1/21/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 1/26/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 1/26/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/8/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Gas Test | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Final | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | FREDDIE RIVERA |
| Final | 7/14/2021 | No Access for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/14/2021 | Approved | FREDDIE RIVERA |
| Green Building Final | 7/14/2021 | Approved | FREDDIE RIVERA |
| METHANE-Final | 7/14/2021 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 7/14/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/14/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 7/14/2021 | Approved | FREDDIE RIVERA |
| Final | 7/23/2021 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Not Ready | ANDREW BEELI |
| Final | 8/2/2021 | OK to Issue CofO | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/2/2021 | SGSOV Approved | FREDDIE RIVERA |