19268 W CALAHAN ST 91324
Certificate Information: 19268 W CALAHAN ST 91324
- Application / Permit
- 20014-20000-01394
- Plan Check / Job No.
- B20VN05080
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 324 sf (IRREGULAR SHAPE) TO AND CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d), AND ADD 20'-6" x 24'-5" (N) TWO-CAR GARAGE TO ADU. AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
- Permit Issued
- Issued on 12/21/2020
- Issuing Office
- Current Status
- CofO Issued on 9/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | SEAN SHAHMIRI |
| Corrections Issued | 4/28/2020 | SEAN SHAHMIRI |
| Green Plans Picked Up | 4/30/2020 | APPLICANT |
| Quality Review Completed | 5/11/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 5/14/2020 | APPLICANT |
| Applicant returned to address corrections | 11/9/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 11/9/2020 | SEAN SHAHMIRI |
| Issued | 12/21/2020 | APPLICANT |
| CofO in Progress | 9/15/2021 | JEFFREY PARD |
| Permit Finaled | 9/30/2021 | JOHN JANSON |
| CofO Issued | 9/30/2021 | JOHN JANSON |
| Permit Finaled | 9/30/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/18/2020 | ADRIAN CASTRO |
| ZA Case | Cleared | 5/20/2020 | DANG NGUYEN |
| Green Code | Cleared | 6/29/2020 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 7/21/2020 | KURT CORRAL |
| Construction within easement | Cleared | 10/3/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/22/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/2/2020 | ADRIAN CASTRO |
Contact Information
| Architect | Dellos,, Wendy Guadalupe; Lic. No.: C36239 | 10411 HASKELL AVENUE GRANADA HILLS, CA 91344 |
| Contractor | Dellos Nick Creations; Lic. No.: 653077-B | 10411 HASKELL AVE GRANADA HILLS, CA 91344 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/4/2021 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 1/20/2021 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2021 | No Access for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Corrections Issued | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 3/23/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 4/1/2021 | Approved | JEFFREY PARD |
| HVAC-Rough | 4/1/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 4/7/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 4/7/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 4/7/2021 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 4/7/2021 | Approved | JEFFREY PARD |
| Reinforced Concrete Frame | 4/7/2021 | Approved | JEFFREY PARD |
| Underground Mechanical | 4/13/2021 | Approved | JEFFREY PARD |
| Insulation | 4/14/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 4/21/2021 | No Access for Inspection | JEFFREY PARD |
| Underground Mechanical | 4/21/2021 | No Access for Inspection | JEFFREY PARD |
| Green Building Rough | 4/22/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 4/22/2021 | Approved | JEFFREY PARD |
| Shower Pan | 4/26/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 5/5/2021 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 5/5/2021 | Partial Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 5/24/2021 | Approved | DEANDRE HOFFMAN |
| Grading Pre-Inspection | 5/25/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 7/30/2021 | Approved | JEFFREY PARD |
| Green Building Final | 8/3/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Final | 8/3/2021 | Approved | JEFFREY PARD |
| HVAC-Final | 8/10/2021 | Approved | JEFFREY PARD |
| PLUMBING-Final | 8/10/2021 | Approved | JEFFREY PARD |
| Final | 8/13/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 8/13/2021 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 8/13/2021 | Approved | JEFFREY PARD |
| Final | 9/14/2021 | OK to Issue CofO | JEFFREY PARD |