4144 N CLEAR VALLEY DR 91436

Certificate Information: 4144 N CLEAR VALLEY DR 91436

Application / Permit
20014-20000-01382
Plan Check / Job No.
B20VN05040
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF IRREGULAR 10' X 30' AND 11' 6" X 5' 4" TO FRONT OF (E) SFD AND 5' 6" X 21' TO FRONT OF (E) ATTACHED 2-CAR GARAGE. NEW 5' HIGH PARAPET WALLS OVER EXISTING FLAT ROOF. ALL WORK DONE PER STRUCTURAL ENGINEERING. SEE COMMENTS***
Permit Issued
Issued on 5/26/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2020 APPLICANT
Assigned to Plan Check Engineer 4/7/2020 GURUNATH NESARAJAH
Corrections Issued 4/8/2020 GURUNATH NESARAJAH
Applicant returned to address corrections 4/24/2020 HAYATO TSUCHIYA
Plan Check Approved 5/8/2020 LUIS RINCON
Issued 5/26/2020 LADBS
Building Plans Picked Up 6/4/2020 APPLICANT
CofO in Progress 10/19/2022 VINCENT HANLEY
CofO Issued 4/25/2023 MICHAEL SMITH
Permit Finaled 4/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/9/2020 ADRIAN CASTRO
ZA Case Cleared 4/9/2020 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 4/14/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 5/7/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Basso,, Alexandre; Lic. No.: C77670 7231 SUMMITROSE ST      TUJUNGA, CA 91042

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/23/2020 Approved RONALD COWAN
Footing/Foundation/Slab 9/25/2020 Corrections Issued RONALD COWAN
Underground Mechanical 9/25/2020 Corrections Issued RONALD COWAN
PLUMBING-Rough 10/5/2020 Corrections Issued RONALD COWAN
Footing/Foundation/Slab 10/8/2020 Partial Approval RONALD COWAN
PLUMBING-Rough 10/8/2020 Partial Approval RONALD COWAN
Deputy Wood Construction 12/21/2020 Partial Approval PAUL CHOPP
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 3/3/2021 Approved RONALD COWAN
HVAC-Rough 3/3/2021 Approved RONALD COWAN
Underground Mechanical 3/3/2021 Approved RONALD COWAN
PLUMBING-Rough 3/31/2021 Approved RONALD COWAN
Wood Frame 3/31/2021 Approved RONALD COWAN
Insulation 4/15/2021 Approved RONALD COWAN
Interior/Exterior Lathing 4/15/2021 Partial Approval RONALD COWAN
Shower Pan 4/15/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 5/28/2021 Approved RONALD COWAN
Drywall Nailing 5/28/2021 Approved RONALD COWAN
Green Building Rough 5/28/2021 Approved RONALD COWAN
Interior/Exterior Lathing 6/8/2021 Approved JESUS RODRIGUEZ
Gas Test 10/12/2021 Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 9/6/2022 Approved VINCENT HANLEY
Final 9/6/2022 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 9/6/2022 Approved VINCENT HANLEY
Green Building Final 9/6/2022 Approved VINCENT HANLEY
HVAC-Final 9/6/2022 Approved VINCENT HANLEY
PLUMBING-Final 9/6/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/6/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 9/6/2022 Approved VINCENT HANLEY
Final 10/19/2022 OK to Issue CofO VINCENT HANLEY