5234 N LEMP AVE 91601
Certificate Information: 5234 N LEMP AVE 91601
- Application / Permit
- 20014-20000-01380
- Plan Check / Job No.
- B20VN05034
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 28.92' X 17.2' FOR BEDROOM/BATHROOM/DEN PER WFPP. See comment
- Permit Issued
- Issued on 5/19/2020
- Issuing Office
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | ALDOUS CHIC |
| Corrections Issued | 4/2/2020 | ALDOUS CHIC |
| Applicant returned to address corrections | 4/13/2020 | ALDOUS CHIC |
| Plan Check Approved | 4/27/2020 | LUIS RINCON |
| Issued | 5/19/2020 | APPLICANT |
| CofO in Progress | 7/15/2022 | THOMAS FINNILA |
| CofO Issued | 7/28/2022 | MICHAEL SMITH |
| Permit Finaled | 7/28/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/6/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2020 | JOHN LIN |
| Sewer availability | Cleared | 4/9/2020 | JOHN LIN |
| Specific Plan | Cleared | 4/17/2020 | MARIANNE KING |
| ZI | Cleared | 4/17/2020 | MARIANNE KING |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/17/2021 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 3/9/2021 | Approved | DANIEL ORRANTE |
| Insulation | 3/10/2021 | Conditional Approval | THOMAS FINNILA |
| Wood Frame | 3/12/2021 | No Access for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/17/2021 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/17/2021 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 5/17/2021 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 5/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/27/2021 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 5/27/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/4/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 6/4/2021 | Approved | THOMAS FINNILA |
| Insulation | 6/10/2021 | Approved | THOMAS FINNILA |
| Wood Frame | 6/10/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 6/16/2021 | Approved | DANIEL ORRANTE |
| Green Building Rough | 6/16/2021 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 7/7/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 12/22/2021 | Approved | MATT KELLERMAN |
| Final | 12/22/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 12/22/2021 | Approved | MATT KELLERMAN |
| Green Building Final | 12/22/2021 | Approved | MATT KELLERMAN |
| MERV13>=Final | 12/22/2021 | Approved | MATT KELLERMAN |
| MERV13>=Rough | 12/22/2021 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2021 | SGSOV Approved | MATT KELLERMAN |
| Smoke Detectors | 12/22/2021 | Approved | MATT KELLERMAN |
| Final | 4/18/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 7/15/2022 | OK to Issue CofO | THOMAS FINNILA |