22415-22417 W CHASE ST 91304

Certificate Information: 22415-22417 W CHASE ST 91304

Application / Permit
20014-20000-01373
Plan Check / Job No.
B20VN05018
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (43'-2 3/16"x 22'-3") 2ND STORY ACCESSORY DWELLING UNIT WITH COVERED PORCH PER GCS 65852.2 (e) (1) (A) & (17'-4"x 19'-6") WORK SHOP/STORAGE TO (E) SINGLE FAMILY DWELLING W/ ATTACHED GARAGE, WORK PER ENGINEER.
Permit Issued
Issued on 12/18/2020
Issuing Office
Current Status
CofO Issued on 2/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 TROY DEGUZMAN
Corrections Issued 4/24/2020 TROY DEGUZMAN
Quality Review Completed 4/30/2020 CHON CHIO KUO
Building Plans Picked Up 4/30/2020 APPLICANT
Green Plans Picked Up 4/30/2020 APPLICANT
Applicant returned to address corrections 7/2/2020 TROY DEGUZMAN
Plan Check Approved 12/18/2020 TROY DEGUZMAN
Issued 12/18/2020 APPLICANT
CofO in Progress 2/10/2022 TROY SANDERS
Permit Finaled 2/25/2022 JOHN JANSON
CofO Issued 2/25/2022 JOHN JANSON
Permit Finaled 2/25/2022 JOHN JANSON

Permit Application Clearance Information

GPI Written Notices Cleared 4/21/2020 TROY DEGUZMAN
Grading Pre-Inspection Cleared 4/21/2020 TROY DEGUZMAN
Green Code Cleared 6/25/2020 MICHAEL AYERS
Address approval Cleared 8/11/2020 ADRIAN CASTRO
Address approval Cleared 8/11/2020 ADRIAN CASTRO
Sewer availability Cleared 8/13/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/18/2020 ADRIAN CASTRO
Distance to fire station Cleared 9/29/2020 MATTHEW CRAIG
Hydrant and Access approval Cleared 9/29/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/29/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 10/29/2020 ADRIAN CASTRO

Contact Information

Architect Tohill,, Kevin Patrick; Lic. No.: C32787 3790 LIGHTNING RIDGE WAY      SIMI VALLEY, CA 93063
Contractor Kullman Bruce D; Lic. No.: 934218-B 2127 RAVENNA STREET      SIMI VALLEY, CA 93065
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2021 Partial Approval DAVID STEPANYAN
Deputy Reinf. Concrete 2/11/2021 Approved DAVID STEPANYAN
Footing/Foundation/Slab 2/19/2021 Partial Approval DAVID STEPANYAN
Deputy Drilled-In Anchors 2/24/2021 Approved DAVID STEPANYAN
Footing/Foundation/Slab 2/26/2021 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 4/21/2021 Not Ready for Inspection DAVID STEPANYAN
Deputy Wood Construction 5/6/2021 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/3/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 6/3/2021 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 6/3/2021 Approved DAVID STEPANYAN
Sewer 6/3/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 6/10/2021 Approved DAVID STEPANYAN
Green Building Rough 6/10/2021 Approved DAVID STEPANYAN
HVAC-Rough 6/10/2021 Approved DAVID STEPANYAN
Insulation 6/16/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/22/2021 Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 9/1/2021 Not Ready for Inspection PETER FOLLING
Drywall Nailing 9/8/2021 Approved DAVID STEPANYAN
Final 9/8/2021 Partial Inspection DAVID STEPANYAN
Footing/Foundation/Slab 9/8/2021 Approved DAVID STEPANYAN
Green Building Final 9/8/2021 Not Ready for Inspection DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 9/8/2021 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 9/8/2021 Corrections Issued DAVID STEPANYAN
Special/Order Compliance 9/8/2021 Partial Inspection MICHAEL PELHAM
ELECTRICAL-Rough 11/2/2021 Approved DAVID STEPANYAN
Pre-Inspection 11/2/2021 Partial Inspection DAVID STEPANYAN
Final 12/22/2021 Corrections Issued DAVID STEPANYAN
Green Building Final 12/22/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 12/22/2021 Corrections Issued DAVID STEPANYAN
Smoke Detectors 12/22/2021 Corrections Issued DAVID STEPANYAN
Final 1/20/2022 Not Ready for Inspection TROY SANDERS
Green Building Final 1/20/2022 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Not Ready TROY SANDERS
Smoke Detectors 1/20/2022 Not Ready for Inspection TROY SANDERS
Final 2/9/2022 OK to Issue CofO TROY SANDERS
Green Building Final 2/9/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 2/9/2022 Approved TROY SANDERS