5434 N CROMER PL 91367
Certificate Information: 5434 N CROMER PL 91367
- Application / Permit
- 20014-20000-01353
- Plan Check / Job No.
- B20VN04986
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (19'-8" X 23'-1") ATTACHED GARAGE TO HABITABLE SPACE. ADD (23'-1" X 24'-2") FOR (N) ATTACHED CARPORT AND ADD (5'-8" X 27'-2") IRREGULAR SHAPE FOR (N) BATHROOMS. REMODEL (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/4/2020
- Issuing Office
- Current Status
- CofO Issued on 11/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2020 | RAPHAEL ROSAS |
| Corrections Issued | 4/3/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/6/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 7/20/2020 | TROY DEGUZMAN |
| Plan Check Approved | 8/4/2020 | ROSENDO MEDINA |
| Issued | 8/4/2020 | APPLICANT |
| CofO in Progress | 11/15/2021 | STEVEN BACK |
| Permit Finaled | 11/16/2021 | MICHAEL SMITH |
| CofO Issued | 11/16/2021 | MICHAEL SMITH |
| Permit Finaled | 11/16/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/16/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 6/29/2020 | ANDRES COVARRUBIAS |
| Grading Pre-Inspection | Cleared | 6/30/2020 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 7/8/2020 | JOHN TRIANTAFYLLOS |
| GPI Written Notices | Cleared | 7/20/2020 | RAPHAEL ROSAS |
Contact Information
| Contractor | Select Design Construction Inc; Lic. No.: 972421-B | P O BOX 2256 RIALTO, CA 92377 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/7/2020 | Partial Approval | HENRY KIM |
| Pre-Inspection | 8/7/2020 | Corrections Issued | HENRY KIM |
| Sewer | 8/7/2020 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 8/17/2020 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 9/1/2020 | Approved | HENRY KIM |
| Pre-Inspection | 9/1/2020 | Corrections Issued | HENRY KIM |
| Structural Steel Frame | 9/1/2020 | Corrections Issued | HENRY KIM |
| Deputy Steel/Welding | 10/29/2020 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 11/20/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 11/20/2020 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 11/30/2020 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 11/30/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 11/30/2020 | Not Ready for Inspection | HENRY KIM |
| Pre-Inspection | 12/1/2020 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 12/3/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 12/3/2020 | Not Ready for Inspection | HENRY KIM |
| Pre-Inspection | 12/3/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 12/14/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 12/14/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 12/14/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2020 | Partial Approval | HENRY KIM |
| Rough-Elec/Plmb/HVAC | 12/29/2020 | Approved | HENRY KIM |
| Structural Steel Frame | 12/29/2020 | Partial Approval | HENRY KIM |
| Insulation | 1/14/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 1/22/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Approved | HENRY KIM |
| Green Building Rough | 1/22/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 1/22/2021 | Approved | HENRY KIM |
| MERV13>=Rough | 1/22/2021 | Approved | HENRY KIM |
| Structural Steel Frame | 1/22/2021 | Approved | HENRY KIM |
| Drywall Nailing | 2/22/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 2/22/2021 | Approved | HENRY KIM |
| Shower Pan | 2/22/2021 | Corrections Issued | HENRY KIM |
| Shower Pan | 2/25/2021 | Corrections Issued | HENRY KIM |
| Shower Pan | 3/2/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 6/10/2021 | Corrections Issued | HENRY KIM |
| Final | 6/10/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 6/10/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 6/10/2021 | Not Ready for Inspection | HENRY KIM |
| HVAC-Final | 6/10/2021 | Corrections Issued | HENRY KIM |
| MERV13>=Final | 6/10/2021 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Final | 6/10/2021 | Not Ready for Inspection | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 6/10/2021 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 6/10/2021 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Final | 7/7/2021 | Corrections Issued | HENRY KIM |
| Final | 7/7/2021 | Corrections Issued | HENRY KIM |
| HVAC-Final | 7/7/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 7/7/2021 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 8/12/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 9/2/2021 | Corrections Issued | HENRY KIM |
| Final | 9/2/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 9/2/2021 | Approved | HENRY KIM |
| Green Building Final | 9/2/2021 | Approved | HENRY KIM |
| HVAC-Final | 9/2/2021 | Corrections Issued | HENRY KIM |
| MERV13>=Final | 9/2/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 9/2/2021 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 9/2/2021 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 9/2/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/13/2021 | Approved | HENRY KIM |
| HVAC-Final | 9/13/2021 | Approved | HENRY KIM |
| MERV13>=Final | 9/13/2021 | Approved | HENRY KIM |
| Final | 11/15/2021 | OK to Issue CofO | STEVEN BACK |
| HVAC-Final | 11/15/2021 | Approved | STEVEN BACK |