1480 S BEVERWIL DR 90035
Certificate Information: 1480 S BEVERWIL DR 90035
- Application / Permit
- 20014-20000-01349
- Plan Check / Job No.
- B20VN04970
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (53'3"x 38'-0") IRR SHAPE 2ND STORY & KEEP PORTION OF (E) 14.5 FT BEDROOM FOOTING @ FRONT OF (E) SINGLE FAMILY DWELLING, AND MAJOR REMODEL WITH NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/28/2021
- Issuing Office
- Current Status
- CofO Issued on 12/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | TROY DEGUZMAN |
| Corrections Issued | 4/16/2020 | TROY DEGUZMAN |
| Quality Review Completed | 4/16/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 5/15/2020 | APPLICANT |
| Green Plans Picked Up | 9/2/2020 | APPLICANT |
| Applicant returned to address corrections | 3/2/2021 | TROY DEGUZMAN |
| Plan Check Approved | 3/31/2021 | TROY DEGUZMAN |
| Plan Check Approved | 4/21/2021 | TROY DEGUZMAN |
| Issued | 4/28/2021 | APPLICANT |
| CofO in Progress | 11/15/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
| CofO Issued | 12/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 10/2/2020 | NIKTA MOUSAVI |
| Low Impact Development | Cleared | 12/15/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/16/2020 | NIKTA MOUSAVI |
| Hydrant and Access approval | Cleared | 1/29/2021 | JOHN CONNEALLY |
| Green Code | Cleared | 2/3/2021 | MICHAEL AYERS |
| Grading Pre-Inspection | Cleared | 3/31/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/24/2021 | Partial Approval | JAVIER RAMOS JR |
| METHANE-Subgrade | 10/12/2021 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 10/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Barrier | 10/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 10/27/2021 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/1/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 11/1/2021 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 11/1/2021 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 11/15/2021 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Barrier | 11/15/2021 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/19/2021 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/20/2021 | No Access for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/22/2021 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 11/23/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Gas Test | 2/1/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 2/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 2/1/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Partial Approval | KEVIN SARGSYAN |
| Gas Test | 2/4/2022 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/4/2022 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 2/4/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/8/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/23/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 2/23/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/28/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 3/11/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 3/11/2022 | Approved | KEVIN SARGSYAN |
| METHANE-Rough | 3/11/2022 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/24/2022 | Approved | EVAN COOPER |
| Shower Pan | 3/24/2022 | Approved | EVAN COOPER |
| Insulation | 3/30/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 4/6/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/6/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/7/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/7/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 10/24/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/24/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| HVAC-Final | 10/28/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 10/28/2022 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 11/2/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 11/2/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 11/4/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 11/4/2022 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 11/4/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 11/14/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |