9825 W LANARK ST 91352

Certificate Information: 9825 W LANARK ST 91352

Application / Permit
20014-20000-01342
Plan Check / Job No.
B20VN04952
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 5'-4" X 11'-6" MASTER BATHROOM ON THE SECOND FLOOR OF THE (E) DWELLING PER ENGINEERING
Permit Issued
Issued on 10/30/2020
Issuing Office
Current Status
CofO Issued on 9/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2020 APPLICANT
Assigned to Plan Check Engineer 4/7/2020 JEFFREY TANGONAN
Corrections Issued 4/7/2020 JEFFREY TANGONAN
Building Plans Picked Up 4/9/2020 APPLICANT
Plan Check Approved 4/17/2020 RAPHAEL ROSAS
Issued 10/30/2020 APPLICANT
CofO in Progress 9/23/2024 DAVID ANDERSON
Permit Finaled 9/26/2024 DANIEL ORRANTE
CofO Issued 9/26/2024 DANIEL ORRANTE
Permit Finaled 9/26/2024 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 4/14/2020 PABLO ESTRADA

Contact Information

Contractor Red Rock General Construction Inc; Lic. No.: 754130-B 17714 CANDIA COURT      GRANADA HILLS, CA 91344
Engineer Barzegar,, Leon; Lic. No.: C41760 2748 HOLLISTER TER      GLENDALE, CA 91206

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 11/9/2020 Approved BEAU COLLINS
PLUMBING-Rough 11/9/2020 Approved BEAU COLLINS
Wood Frame 11/9/2020 Corrections Issued BEAU COLLINS
BUILDING-Rough-Frame 11/25/2020 Approved GREGG CUMMINGS
HVAC-Rough 11/25/2020 Approved GREGG CUMMINGS
Insulation 11/25/2020 Approved GREGG CUMMINGS
Drywall Nailing 12/2/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 12/2/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 12/18/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/9/2021 Approved BEAU COLLINS
Final 4/9/2021 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 4/9/2021 Approved BEAU COLLINS
Green Building Final 4/9/2021 Not Ready for Inspection BEAU COLLINS
Green Building Rough 4/9/2021 Approved BEAU COLLINS
Smoke Detectors 4/9/2021 Approved BEAU COLLINS
Final 9/20/2024 OK to Issue CofO DAVID ANDERSON
Green Building Final 9/20/2024 Approved DAVID ANDERSON