16052-16054 W RAYEN ST 91343

Certificate Information: 16052-16054 W RAYEN ST 91343

Application / Permit
20014-20000-01338
Plan Check / Job No.
B20VN04939
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20'-2" X 20'-8" ATTACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 5/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2020 APPLICANT
Assigned to Plan Check Engineer 4/1/2020 JENNIFER LEE
Corrections Issued 4/7/2020 JENNIFER LEE
Plan Check Approved 4/28/2020 HAYATO TSUCHIYA
Issued 5/18/2020 LADBS
CofO in Progress 9/25/2020 WILLIAM KUEHN
Permit Finaled 1/20/2021 MICHAEL SMITH
CofO Issued 1/20/2021 MICHAEL SMITH
Permit Finaled 1/20/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/9/2020 ADRIAN CASTRO
Sewer availability Cleared 4/9/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/10/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 4/14/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/4/2020 Approved JOHN HAYES
Footing/Foundation/Slab 6/10/2020 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 6/19/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/2/2020 Corrections Issued BEAU COLLINS
ELECTRICAL-Rough 7/2/2020 Not Ready for Inspection BEAU COLLINS
Green Building Rough 7/2/2020 Not Ready for Inspection BEAU COLLINS
PLUMBING-Rough 7/2/2020 Not Ready for Inspection BEAU COLLINS
ELECTRICAL-Rough 7/7/2020 Approved DANIEL DREW
HVAC-Rough 7/7/2020 Approved DANIEL DREW
PLUMBING-Rough 7/7/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 7/9/2020 Approved MICHEL ABAJAN
Green Building Rough 7/9/2020 Approved MICHEL ABAJAN
Insulation 7/9/2020 Conditional Approval MICHEL ABAJAN
Interior/Exterior Lathing 7/9/2020 Approved MICHEL ABAJAN
Drywall Nailing 7/13/2020 Approved MICHEL ABAJAN
Shower Pan 7/13/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/16/2020 Approved DANIEL ORRANTE
ELECTRICAL-Final 8/20/2020 Approved DANIEL DREW
Final 8/20/2020 Corrections Issued DANIEL DREW
Green Building Final 8/20/2020 Not Ready for Inspection DANIEL DREW
HVAC-Final 8/20/2020 Approved DANIEL DREW
PLUMBING-Final 8/20/2020 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 8/20/2020 SGSOV Approved DANIEL DREW
Smoke Detectors 8/20/2020 Approved DANIEL DREW
Final 9/24/2020 OK to Issue CofO WILLIAM KUEHN
Green Building Final 9/24/2020 Approved WILLIAM KUEHN