5766 N ENCINO AVE 91316

Certificate Information: 5766 N ENCINO AVE 91316

Application / Permit
20014-20000-01327
Plan Check / Job No.
B20VN04897
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12-8" X 16'-4" ADDITION TO (E) ATTACHED GARAGE IN (E) 1-STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 9/11/2020
Issuing Office
Current Status
CofO Issued on 4/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 SERGIO MUNIZ
Corrections Issued 4/13/2020 SERGIO MUNIZ
Quality Review Completed 4/16/2020 OMID HEDAYAT
Green Plans Picked Up 4/27/2020 APPLICANT
Building Plans Picked Up 4/30/2020 APPLICANT
Applicant returned to address corrections 8/21/2020 SERGIO MUNIZ
Applicant returned to address corrections 9/4/2020 SERGIO MUNIZ
Applicant returned to address corrections 9/9/2020 SERGIO MUNIZ
Plan Check Approved 9/11/2020 SERGIO MUNIZ
Issued 9/11/2020 APPLICANT
CofO in Progress 4/22/2021 STEVEN BACK
Permit Finaled 4/30/2021 JOHN JANSON
CofO Issued 4/30/2021 JOHN JANSON
Permit Finaled 4/30/2021 JOHN JANSON

Permit Application Clearance Information

Low Impact Development Cleared 6/12/2020 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 6/17/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/23/2020 ADRIAN CASTRO
Green Code Cleared 8/13/2020 MICHAEL AYERS

Contact Information

Contractor Construction By Maya Inc; Lic. No.: 1034501-B 4872 TOPANGA CANYON BLVD #286      WOODLAND HILLS, CA 91364
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/14/2020 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 11/4/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 11/10/2020 Corrections Issued DAVID SANDOVAL
BUILDING-Rough-Frame 11/25/2020 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 11/25/2020 Approved STEVEN BACK
Footing/Foundation/Slab 11/25/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 1/8/2021 Not Ready for Inspection RONALD COWAN
Green Building Rough 1/8/2021 Not Ready for Inspection RONALD COWAN
Pre-Inspection 1/12/2021 No Access for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 2/3/2021 Approved STEVEN BACK
Drywall Nailing 2/3/2021 Approved STEVEN BACK
Final 2/3/2021 Corrections Issued STEVEN BACK
Green Building Final 2/3/2021 Not Ready for Inspection STEVEN BACK
Green Building Rough 2/3/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/3/2021 SGSOV Not Ready STEVEN BACK
Smoke Detectors 2/3/2021 Approved STEVEN BACK
Final 4/22/2021 OK to Issue CofO STEVEN BACK
Green Building Final 4/22/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 4/22/2021 SGSOV Approved STEVEN BACK