961-963 W 61ST ST 90044

Certificate Information: 961-963 W 61ST ST 90044

Application / Permit
20014-20000-01326
Plan Check / Job No.
B20VN04896
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(2) Duplex
Work Description
PROPOSED 3-STORY DUPLEX WITH AN ATTACHED 4-CAR GARAGE.
Permit Issued
Issued on 6/17/2022
Issuing Office
Current Status
CofO Issued on 3/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 MICHAEL LOPEZ
Green Plans Picked Up 4/16/2020 APPLICANT
Corrections Issued 4/23/2020 MICHAEL LOPEZ
Quality Review Completed 5/12/2020 QUAN NGHIEM
Building Plans Picked Up 5/14/2020 APPLICANT
Applicant returned to address corrections 11/3/2021 MICHAEL LOPEZ
Applicant returned to address corrections 3/9/2022 MICHAEL LOPEZ
Plan Check Approved 5/10/2022 MICHAEL LOPEZ
Issued 6/17/2022 APPLICANT
CofO in Progress 3/15/2024 JAMES POWERS
Permit Finaled 3/15/2024 RAFAEL ESPINOZA
CofO Issued 3/15/2024 RAFAEL ESPINOZA
Permit Finaled 3/15/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

CPC Cleared 6/5/2020 KENTON TRINH
CPC Cleared 6/5/2020 KENTON TRINH
Miscellaneous Cleared 6/5/2020 KENTON TRINH
Redevelopment Project Area Cleared 8/14/2020 GRACIELA ACOSTA
Hydrant and Access approval Cleared 11/10/2020 KURT CORRAL
Low Impact Development Cleared 5/24/2021 ANDRES COVARRUBIAS
Address approval Cleared 6/3/2021 STEVE MELGAR
Community Plan Implem. Overlay Cleared 6/3/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 6/8/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/11/2021 STEVE MELGAR
Highway dedication Cleared 6/11/2021 STEVE MELGAR
Sewer availability Cleared 6/11/2021 STEVE MELGAR
Permit Cleared 8/10/2021 RENZ SORIANO
Green Code Cleared 9/1/2021 DAVID MATSON
Community Plan Implem. Overlay Cleared 11/1/2021 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 12/16/2021 WALTER RAMIREZ
Community Plan Implem. Overlay Cleared 12/21/2021 PETE EYRE
Trees in Parkway Cleared 12/28/2021 ADALBERTO VERA
Community Plan Implem. Overlay Cleared 1/6/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Boranian,, Paul Darian; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367
Engineer Haddad,, Raymond Mounir; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Sunna,, Nadim; Lic. No.: C84197 27035 MARISCAL LN      MISSION VIEJO, CA 92691

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/1/2022 Approved JOAQUIN GREENOUGH
Pre-Inspection 9/13/2022 Approved JAMES POWERS
BUILDING-Rough-Frame 10/5/2022 Not Ready for Inspection JAMES POWERS
Final 10/5/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/5/2022 Not Ready for Inspection JAMES POWERS
Green Building Final 10/5/2022 Not Ready for Inspection JAMES POWERS
Green Building Rough 10/5/2022 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Not Ready JAMES POWERS
Service/Power Release 10/5/2022 Not Ready for Inspection JAMES POWERS
Smoke Detectors 10/5/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 10/5/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/15/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/21/2022 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 11/30/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Partial Approval TED RIES
Wood Frame 2/6/2023 Partial Approval TED RIES
Interior/Exterior Lathing 2/24/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 3/8/2023 Approved JAMES POWERS
Insulation 4/24/2023 Approved JAMES POWERS
Insulation 4/27/2023 Approved JAMES POWERS
Light Gage Steel Frame 4/27/2023 Approved JAMES POWERS
Drywall Nailing 5/1/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/1/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 5/3/2023 Approved JAMES POWERS
Interior/Exterior Lathing 5/8/2023 Approved JAMES POWERS
BUILDING-Rough-Frame 9/20/2023 Approved JAMES POWERS
Final 9/20/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/20/2023 Approved JAMES POWERS
Green Building Final 9/20/2023 Approved JAMES POWERS
Green Building Rough 9/20/2023 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/20/2023 SGSOV Approved JAMES POWERS
Smoke Detectors 9/20/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 9/20/2023 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/2/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 10/6/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/12/2023 Partial Approval JAMES POWERS
Special/Order Compliance 10/20/2023 Conditional Approval LARRY ARNICK
Final 11/13/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/13/2023 Not Ready for Inspection JAMES POWERS
Service/Power Release 11/13/2023 Not Ready for Inspection JAMES POWERS
Final 12/21/2023 OK for TCO JAMES POWERS
Footing/Foundation/Slab 12/21/2023 Approved JAMES POWERS
Final 3/15/2024 Conditional Approval JAMES POWERS
Final 3/15/2024 OK to Issue CofO JAMES POWERS
Service/Power Release 3/15/2024 Approved JAMES POWERS
T-Bar Ceiling 3/15/2024 Approved JAMES POWERS