5322 N AMESTOY AVE 91316
Certificate Information: 5322 N AMESTOY AVE 91316
- Application / Permit
- 20014-20000-01309
- Plan Check / Job No.
- B20VN04855
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 30'-0" X 19'-4" IRREG SHAPED ADDITION TO AND CONVERT (E) DETACHED POOL HOUSE TO ACCESSORY DWELLING UNIT (939 SQ FT)
- Permit Issued
- Issued on 12/2/2020
- Issuing Office
- Current Status
- Issued on 12/2/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 3/19/2020 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/26/2020 | APPLICANT |
| Applicant returned to address corrections | 11/25/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/1/2020 | JEROME MAGAT PALMA |
| Issued | 12/2/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/4/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 10/22/2020 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 11/6/2020 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 11/30/2020 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/24/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 1/4/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 2/4/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Approved | STEVEN BACK |
| Rough-Elec/Plmb/HVAC | 3/22/2021 | Approved | STEVEN BACK |
| Shower Pan | 3/22/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 4/20/2021 | Approved | STEVEN BACK |
| Green Building Rough | 4/20/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 4/20/2021 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 5/3/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/3/2021 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 5/3/2021 | Approved | ADAM ESCOTO |
| Special/Order Compliance | 5/3/2021 | Approved | ADAM ESCOTO |
| Insulation | 5/7/2021 | Approved | JESUS PINEDA |
| Pre-Inspection | 5/7/2021 | Partial Approval | JUSTIN HAWLEY |