5433 N SHOUP AVE 91367

Certificate Information: 5433 N SHOUP AVE 91367

Application / Permit
20014-20000-01307
Plan Check / Job No.
B20VN04853
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
26'6" X 15'6"ADDITION OF BEDROOM/ BATHROOM AND CLOSET & REMODEL TO (E) SFD. ALL WORK PER ENGINEER.
Permit Issued
Issued on 5/26/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 PINANK PATEL
Corrections Issued 3/20/2020 PINANK PATEL
Building Plans Picked Up 3/23/2020 APPLICANT
Plan Check Approved 5/7/2020 PINANK PATEL
Issued 5/26/2020 LADBS
CofO in Progress 8/22/2021 TROY SANDERS
Permit Finaled 10/6/2021 JOHN JANSON
CofO Issued 10/6/2021 JOHN JANSON
Permit Finaled 10/6/2021 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/1/2020 JOHN LIN
Sewer availability Cleared 4/1/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 4/6/2020 GABRIEL ROBLES
Grading Pre-Inspection Cleared 5/7/2020 PINANK PATEL

Contact Information

Contractor Owner-Builder       ,
Engineer Lopez,, Mauricio Jose; Lic. No.: C36801 1391 N THIRD AVE      UPLAND, CA 91786

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/28/2020 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 7/28/2020 Not Ready for Inspection TROY SANDERS
Excavation/Setback/Form/Re-Bar 7/29/2020 Not Ready for Inspection TROY SANDERS
Excavation/Setback/Form/Re-Bar 7/30/2020 Not Ready for Inspection DONALD SUNSERI
Footing/Foundation/Slab 7/30/2020 Corrections Issued DONALD SUNSERI
Excavation/Setback/Form/Re-Bar 8/3/2020 Approved TROY SANDERS
PLUMBING-Rough 8/14/2020 Partial Approval TROY SANDERS
Wood Frame 8/14/2020 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 10/19/2020 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 10/19/2020 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Approved TROY SANDERS
Green Building Rough 10/19/2020 Not Ready for Inspection TROY SANDERS
HVAC-Rough 10/19/2020 Approved TROY SANDERS
MERV13>=Rough 10/19/2020 Approved TROY SANDERS
PLUMBING-Rough 10/19/2020 Approved TROY SANDERS
Wood Frame 10/19/2020 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 10/29/2020 Approved TROY SANDERS
Green Building Rough 10/29/2020 Approved TROY SANDERS
Insulation 10/29/2020 Approved TROY SANDERS
Drywall Nailing 11/5/2020 Approved TROY SANDERS
Interior/Exterior Lathing 11/5/2020 Approved TROY SANDERS
Shower Pan 11/16/2020 Approved TROY SANDERS
Gas Test 12/4/2020 Approved TROY SANDERS
ELECTRICAL-Final 5/28/2021 Approved TROY SANDERS
Final 5/28/2021 Corrections Issued TROY SANDERS
Footing/Foundation/Slab 5/28/2021 Approved TROY SANDERS
Gas Test 5/28/2021 Approved TROY SANDERS
Green Building Final 5/28/2021 Corrections Issued TROY SANDERS
HVAC-Final 5/28/2021 Approved TROY SANDERS
MERV13>=Final 5/28/2021 Approved TROY SANDERS
PLUMBING-Final 5/28/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/28/2021 SGSOV Approved TROY SANDERS
Service/Power Release 5/28/2021 Approved TROY SANDERS
Smoke Detectors 5/28/2021 Approved TROY SANDERS
Final 8/20/2021 OK to Issue CofO TROY SANDERS
Green Building Final 8/20/2021 Approved TROY SANDERS