3535 N HILLVIEW PL 90032

Certificate Information: 3535 N HILLVIEW PL 90032

Application / Permit
20014-20000-01288
Plan Check / Job No.
B20VN04785
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 39'6" X 29'6" TWO STORY SFD WITH ATTACHED BASEMENT ENTRY AND BASEMENT TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/26/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 RARES BODEA
Green Plans Picked Up 4/17/2020 APPLICANT
Corrections Issued 4/23/2020 RARES BODEA
Quality Review Completed 4/30/2020 STEVEN KIM
Building Plans Picked Up 4/30/2020 APPLICANT
Applicant returned to address corrections 7/15/2020 RARES BODEA
Applicant returned to address corrections 10/24/2022 RARES BODEA
Applicant returned to address corrections 12/13/2022 RARES BODEA
Applicant returned to address corrections 1/23/2023 RARES BODEA
Applicant returned to address corrections 2/1/2023 RARES BODEA
Plan Check Approved 2/3/2023 RARES BODEA
No Progress 2/7/2023 RARES BODEA
Plan Check Approved 2/8/2023 RARES BODEA
Issued 4/26/2023 APPLICANT
CofO in Progress 10/7/2025 LILIANA PORTILLO
Permit Finaled 10/9/2025 DEROLD HAUFF
CofO Issued 10/9/2025 DEROLD HAUFF
Permit Finaled 10/9/2025 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 3/31/2021 JASON CHAN
"D" conditions Cleared 4/6/2021 JASON CHAN
"Q" conditions Cleared 4/6/2021 JASON CHAN
Address approval Cleared 4/14/2021 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 4/14/2021 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 4/14/2021 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 4/14/2021 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 4/14/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 4/15/2021 CECILIO NAVARRO
Sewer availability Cleared 4/15/2021 CECILIO NAVARRO
Distance to fire station Cleared 5/21/2021 KURT CORRAL
Hydrant and Access approval Cleared 5/21/2021 KURT CORRAL
Green Code Cleared 6/3/2021 DAVID MATSON
BHO/Hillside ordinance Cleared 6/23/2022 TREVOR QUAN
Permit Cleared 7/20/2022 JEANETTE VONG
Low Impact Development Cleared 8/12/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/22/2022 TREVOR QUAN
GPI Written Notices Cleared 10/24/2022 RARES BODEA
Grading Pre-Inspection Cleared 10/24/2022 RARES BODEA
Trees in Parkway Cleared 12/19/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/8/2023 Partial Inspection AMY COLIN
Pre-Inspection 8/8/2023 Partial Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 3/7/2024 Not Ready for Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 3/8/2024 Corrections Issued LILIANA PORTILLO
Special/Order Compliance 3/8/2024 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/18/2024 Partial Approval BRENDAN MORELLI
Deputy Reinf. Concrete 3/22/2024 Conditional Approval LILIANA PORTILLO
Grading Pre-Inspection 4/2/2024 Partial Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/17/2024 Conditional Approval LILIANA PORTILLO
Deputy Reinf. Concrete 4/19/2024 Conditional Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 4/24/2024 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 5/10/2024 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 5/15/2024 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 5/20/2024 Not Ready for Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 5/29/2024 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 6/5/2024 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 6/14/2024 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 7/1/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 7/12/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 7/25/2024 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 7/30/2024 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 7/31/2024 Approved LILIANA PORTILLO
Footing/Foundation/Slab 8/15/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 8/27/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 11/8/2024 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 11/8/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 11/8/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 11/8/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 11/8/2024 Approved LILIANA PORTILLO
Deputy Wood Construction 11/14/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 11/14/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 11/20/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 11/20/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Conditional Approval LILIANA PORTILLO
HVAC-Rough 11/25/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 12/3/2024 Conditional Approval LILIANA PORTILLO
HVAC-Rough 12/3/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/3/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 12/6/2024 Partial Approval LILIANA PORTILLO
Shower Pan 12/6/2024 Approved LILIANA PORTILLO
Green Building Rough 12/13/2024 Approved LILIANA PORTILLO
Insulation 12/13/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 12/26/2024 Approved LILIANA PORTILLO
Drywall Nailing 1/3/2025 Approved JOSH MEISTER
Insulation 1/3/2025 Approved JOSH MEISTER
BUILDING-Rough-Frame 4/18/2025 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Final 4/18/2025 Not Ready for Inspection LILIANA PORTILLO
Final 4/18/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 4/18/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 4/18/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 4/18/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 4/18/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 4/18/2025 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 7/18/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/18/2025 Not Ready for Inspection LILIANA PORTILLO
Final 7/18/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 7/18/2025 Approved LILIANA PORTILLO
HVAC-Final 7/18/2025 Approved LILIANA PORTILLO
PLUMBING-Final 7/18/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 7/18/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 7/18/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 9/25/2025 Approved BRENDAN MORELLI
Final 9/25/2025 Not Ready for Inspection BRENDAN MORELLI
HVAC-Final 9/25/2025 Approved BRENDAN MORELLI
PLUMBING-Final 9/25/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 9/25/2025 Not Ready for Inspection BRENDAN MORELLI
Final 10/6/2025 OK to Issue CofO LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/6/2025 SGSOV Approved LILIANA PORTILLO
Service/Power Release 10/6/2025 Approved LILIANA PORTILLO