2543 S PATRICIA AVE 90064

Certificate Information: 2543 S PATRICIA AVE 90064

Application / Permit
20014-20000-01281
Plan Check / Job No.
B20VN04776
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 35'11" X 11'10" TRELLIS AND INTERIRO REMDOEL FOR (E) SFD W/ ATT. GARAGE. ALL WORK PER ENGINEER.
Permit Issued
Issued on 6/5/2020
Issuing Office
Current Status
CofO Issued on 10/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/18/2020 PINANK PATEL
Corrections Issued 3/19/2020 PINANK PATEL
Plan Check Approved 5/14/2020 PINANK PATEL
Issued 6/5/2020 APPLICANT
Building Plans Picked Up 6/10/2020 APPLICANT
CofO in Progress 9/23/2021 KEVIN SARGSYAN
Permit Finaled 10/20/2021 KENNETH NAGLE
CofO Issued 10/20/2021 KENNETH NAGLE
Permit Finaled 10/20/2021 KENNETH NAGLE

Permit Application Clearance Information

Specific Plan Cleared 4/8/2020 DYLAN SITTIG
ZI Cleared 4/8/2020 DYLAN SITTIG
Grading Pre-Inspection Cleared 5/14/2020 BRIAN MILLER

Contact Information

Contractor Supreme Builders & Associates; Lic. No.: 991300-B 411 E HUNTINGTON DR   STE #107-307    ARCADIA, CA 91006
Engineer Samadzadeh,, Ali Reza; Lic. No.: C87661 20655 SHERMAN WAY #5      LOS ANGELES, CA 91306

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/7/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 8/7/2020 Corrections Issued KEVIN SARGSYAN
Deputy Wood Construction 8/11/2020 Conditional Approval KEVIN SARGSYAN
Green Building Rough 8/11/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 8/11/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 8/11/2020 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/12/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 8/19/2020 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/19/2020 Partial Approval KEVIN SARGSYAN
Green Building Rough 8/19/2020 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 8/28/2020 Corrections Issued KEVIN SARGSYAN
Shower Pan 9/1/2020 Partial Approval KENNETH NAGLE
Drywall Nailing 9/8/2020 Approved KEVIN SARGSYAN
Shower Pan 9/8/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/9/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 9/11/2020 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 9/11/2020 Approved KEVIN SARGSYAN
METHANE-Subgrade 9/11/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 9/15/2020 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 9/17/2020 Partial Approval KEVIN SARGSYAN
Pre-Inspection 1/19/2021 Partial Inspection KEVIN SARGSYAN
Structural Steel Frame 1/19/2021 Partial Inspection KEVIN SARGSYAN
Deputy Drilled-In Anchors 1/28/2021 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 1/29/2021 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 1/29/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 2/4/2021 Corrections Issued KEVIN SARGSYAN
Wood Frame 2/4/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 2/8/2021 Approved KEVIN SARGSYAN
Deputy Reinf. Concrete 2/10/2021 Conditional Approval KEVIN SARGSYAN
Interior/Exterior Lathing 5/17/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 8/27/2021 Approved KEVIN SARGSYAN
Final 8/27/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 8/27/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 8/27/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/27/2021 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 8/27/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 9/9/2021 Corrections Issued KEVIN SARGSYAN
Final 9/9/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Final 9/9/2021 Approved KEVIN SARGSYAN
HVAC-Final 9/9/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 9/9/2021 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 9/9/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Final 9/23/2021 Approved KEVIN SARGSYAN
Final 9/23/2021 OK to Issue CofO KEVIN SARGSYAN
HVAC-Final 9/23/2021 Approved KEVIN SARGSYAN
PLUMBING-Final 9/23/2021 Approved KEVIN SARGSYAN