121 1/2 N SYCAMORE AVE 90036
Certificate Information: 121 1/2 N SYCAMORE AVE 90036
- Application / Permit
- 20014-20000-01270
- Plan Check / Job No.
- B20VN04696
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 22'-11" x 52' IRREGULAR SHAPE SECOND STORY OVER (E) GARAGE TO BE A (N) ACESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/30/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | SEAN SHAHMIRI |
| Green Plans Picked Up | 4/10/2020 | APPLICANT |
| Corrections Issued | 4/15/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 4/24/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 4/30/2020 | APPLICANT |
| Applicant returned to address corrections | 10/14/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 10/14/2020 | SEAN SHAHMIRI |
| Issued | 10/30/2020 | APPLICANT |
| CofO in Progress | 9/14/2021 | JOSEPH MCGARRY |
| Permit Finaled | 9/22/2021 | DEROLD HAUFF |
| CofO Issued | 9/22/2021 | DEROLD HAUFF |
| Permit Finaled | 9/22/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 4/23/2020 | AARON COSTA |
| Tenant Habitability Plan | Cleared | 5/6/2020 | PHILLIP MUNGUIA |
| Address approval | Cleared | 5/20/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 5/20/2020 | RENZ SORIANO |
| "Q" conditions | Cleared | 5/26/2020 | TERRI OSBORNE |
| Miscellaneous | Cleared | 5/26/2020 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 6/2/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 7/2/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/24/2020 | CECILIO NAVARRO |
| Abandoned oil well | Cleared | 8/27/2020 | MATTHEW CRAIG |
| Abandoned oil well approval | Cleared | 8/27/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Ben Porat Moshe M; Lic. No.: 963181-B | P O BOX 48603 LOS ANGELES, CA 90048 |
| Engineer | John, P Sin; Lic. No.: C91162 | JSIN01123@GMAIL.COM , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/4/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 1/4/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 1/4/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2021 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/25/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 2/25/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 2/25/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| METHANE-Rough | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/25/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Underground Mechanical | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 3/1/2021 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/10/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/10/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/10/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 3/10/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/10/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/10/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 3/16/2021 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/16/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 3/16/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 5/13/2021 | Approved | JOSEPH MCGARRY |
| Gas Test | 5/13/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 5/13/2021 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 5/13/2021 | SGSOV Not Ready | JOSEPH MCGARRY |
| Service/Power Release | 5/13/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Drywall Nailing | 5/28/2021 | Approved | JOSEPH MCGARRY |
| Final | 5/28/2021 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 5/28/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 5/28/2021 | Approved | JOSEPH MCGARRY |
| Final | 7/22/2021 | Conditional Approval | CHARLES BOGHOSKHAN |
| Final | 9/3/2021 | OK to Issue CofO | JOSEPH MCGARRY |
| Service/Power Release | 9/3/2021 | Approved | JOSEPH MCGARRY |