1410 S THAYER AVE 90024
Certificate Information: 1410 S THAYER AVE 90024
- Application / Permit
- 20014-20000-01264
- Plan Check / Job No.
- B20VN04685
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO (E) SFD. REMOVE EXISTING DWELLING WITH ONLY BASEMENT GARAGE TO REMAIN AND RECONSTRUCT DWELLING WITH ADDITION. DWELLING AND GARAGE TO BE SPRINKLERED THROUGHOUT NFPA-13D
- Permit Issued
- Issued on 8/20/2021
- Issuing Office
- Current Status
- CofO Issued on 5/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | JESSE ARELLANO |
| Corrections Issued | 4/14/2020 | JESSE ARELLANO |
| Quality Review Completed | 4/21/2020 | BILL STUTSMAN |
| Green Plans Picked Up | 5/4/2020 | APPLICANT |
| Applicant returned to address corrections | 9/11/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 9/16/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/16/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/19/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/22/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/23/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/3/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/15/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/17/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 7/8/2021 | JESSE ARELLANO |
| Plan Check Approved | 8/20/2021 | JESSE ARELLANO |
| Issued | 8/20/2021 | APPLICANT |
| Building Plans Picked Up | 8/30/2021 | APPLICANT |
| CofO in Progress | 4/25/2025 | KIRK SANDERS |
| Permit Finaled | 5/1/2025 | RICHARD STEINBACH |
| CofO Issued | 5/1/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/1/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | DINAH GARIN |
| Sewer availability | Cleared | 9/24/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 12/1/2020 | MATTHEW CRAIG |
| Specific Plan | Cleared | 12/2/2020 | PETE EYRE |
| Methane Ordinance | Cleared | 12/7/2020 | ANDREW KO |
| Low Impact Development | Cleared | 3/24/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 4/1/2021 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 4/22/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 6/3/2021 | JESSE ARELLANO |
| GPI Written Notices | Cleared | 6/9/2021 | JESSE ARELLANO |
| Construction near power lines | Cleared | 6/14/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/14/2021 | RIDWAN HARDY |
| Green Code | Cleared | 8/20/2021 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 120 W WILSON AVE 1550 GLENDALE, CA 91203 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 11/19/2021 | Partial Inspection | OGANES TARAKHCHYAN |
| Pre-Inspection | 3/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 3/14/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/15/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Special/Order Compliance | 3/16/2022 | Partial Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 3/18/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/22/2022 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Barrier | 4/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 4/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/26/2022 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 4/26/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 4/26/2022 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 5/2/2022 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Barrier | 5/2/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 5/2/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 5/10/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/16/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/27/2022 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Rough | 7/7/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/13/2022 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 8/1/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Conditional Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/14/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 2/14/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 2/22/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 3/1/2023 | Approved | CLAYTON GRAHAM |
| METHANE-Rough | 3/1/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/7/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/13/2023 | Conditional Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Wood Construction | 3/14/2023 | Conditional Approval | CLAYTON GRAHAM |
| Deputy Wood Construction | 3/17/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Wood Frame | 3/20/2023 | Not Ready for Inspection | JEREMY TODD |
| Deputy Wood Construction | 3/22/2023 | Conditional Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Corrections Issued | JEREMY TODD |
| BUILDING-Rough-Frame | 3/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/28/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 3/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Rough | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 4/3/2023 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | JEREMY TODD |
| Green Building Rough | 4/5/2023 | Approved | JEREMY TODD |
| Verify Sprinkler Sign Off | 4/5/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 4/13/2023 | Conditional Approval | JEREMY TODD |
| ELECTRICAL-Rough | 4/13/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 4/13/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/13/2023 | Not Ready for Inspection | JEREMY TODD |
| Wood Frame | 4/18/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | JESUS PINEDA |
| Insulation | 4/21/2023 | Approved | JESUS PINEDA |
| Wood Frame | 4/21/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/1/2023 | Approved | JESUS PINEDA |
| Shower Pan | 5/3/2023 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 5/10/2023 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 5/16/2023 | Partial Approval | JEREMY TODD |
| Interior/Exterior Lathing | 5/24/2023 | Approved | JESUS PINEDA |
| Shower Pan | 5/24/2023 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 9/29/2023 | Partial Approval | BRENDAN LOONEY |
| Sewer | 9/29/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 10/13/2023 | Partial Approval | BEN MOLSTAD |
| Grading Pre-Inspection | 12/1/2023 | Conditional Approval | BEN MOLSTAD |
| Grading Pre-Inspection | 12/5/2023 | Corrections Issued | BEN MOLSTAD |
| Grading Pre-Inspection | 12/8/2023 | Approved | BEN MOLSTAD |
| Gas Test | 1/16/2024 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 1/16/2024 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/23/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 1/23/2024 | Partial Approval | MEL KHACHATOURIAN |
| Service/Power Release | 1/23/2024 | Approved | MEL KHACHATOURIAN |
| Gas Test | 2/7/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Gas Test | 2/8/2024 | Approved | MEL KHACHATOURIAN |
| Final | 2/29/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Final | 2/29/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 2/29/2024 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 3/21/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 3/21/2024 | Approved | STEPHANIE SWANSON |
| Final | 5/28/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 5/28/2024 | Approved | KIRK SANDERS |
| Final | 4/24/2025 | OK to Issue CofO | KIRK SANDERS |