22745 W ERWIN ST 91367

Certificate Information: 22745 W ERWIN ST 91367

Application / Permit
20014-20000-01258
Plan Check / Job No.
B20VN04662
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION of 16'5"x19'11" (322 SF) Recreation room, and a 6'5"x9'3" exterior access only full bathroom.
Permit Issued
Issued on 3/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2020 APPLICANT
Assigned to Plan Check Engineer 3/17/2020 LUIS RINCON
Plan Check Approved 3/17/2020 LUIS RINCON
Issued 3/17/2020 LADBS
CofO in Progress 12/10/2020 TROY SANDERS
CofO Issued 12/11/2020 JOHN JANSON
Permit Finaled 12/11/2020 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/17/2020 LEE GUILBEAUX
Grading Pre-Inspection Cleared 3/17/2020 BARTON HOLMES
Roof/Waste drainage to street Cleared 3/17/2020 LEE GUILBEAUX

Contact Information

Contractor Elite Remodeling Group Inc; Lic. No.: 1023088-B 22287 MULHOLLAND HWY      CALABASAS, CA 91302
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/13/2020 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 8/17/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 9/22/2020 Approved TROY SANDERS
ELECTRICAL-Rough 9/22/2020 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Approved TROY SANDERS
Green Building Rough 9/22/2020 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 9/22/2020 Approved TROY SANDERS
Green Building Rough 10/7/2020 Approved TROY SANDERS
Insulation 10/7/2020 Approved TROY SANDERS
Interior/Exterior Lathing 10/7/2020 Approved TROY SANDERS
Drywall Nailing 10/19/2020 Approved TROY SANDERS
Interior/Exterior Lathing 10/19/2020 Approved TROY SANDERS
Shower Pan 10/19/2020 Approved TROY SANDERS
ELECTRICAL-Final 12/10/2020 Approved TROY SANDERS
Final 12/10/2020 OK to Issue CofO TROY SANDERS
Footing/Foundation/Slab 12/10/2020 Approved TROY SANDERS
Green Building Final 12/10/2020 Approved TROY SANDERS
HVAC-Final 12/10/2020 Approved TROY SANDERS
PLUMBING-Final 12/10/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV Approved TROY SANDERS
Smoke Detectors 12/10/2020 Approved TROY SANDERS