21038 W RUNNYMEDE ST 91303
Certificate Information: 21038 W RUNNYMEDE ST 91303
- Application / Permit
- 20014-20000-01256
- Plan Check / Job No.
- B20VN04658
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Irr. 23'-10" x 25' (464 sf) addition to the single-family dwelling with attached garage.
- Permit Issued
- Issued on 3/17/2020
- Issuing Office
- Valley
- Current Status
- Issued on 3/17/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2020 | LUIS RINCON |
| Plan Check Approved | 3/17/2020 | ANGELICA MARTINEZ |
| Issued | 3/17/2020 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 3/17/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/17/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/3/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 4/3/2020 | Not Ready for Inspection | HENRY KIM |
| Pre-Inspection | 4/3/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 5/22/2020 | Not Ready for Inspection | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 5/22/2020 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 5/22/2020 | Not Ready for Inspection | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 5/26/2020 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 5/26/2020 | Approved | HENRY KIM |
| Pre-Inspection | 5/26/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 6/12/2020 | Partial Approval | HENRY KIM |
| Insulation | 6/12/2020 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 6/18/2020 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2020 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 6/29/2020 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 6/29/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 6/29/2020 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 7/1/2020 | Approved | HENRY KIM |
| HVAC-Rough | 7/1/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 7/2/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2020 | Approved | HENRY KIM |
| Green Building Rough | 7/2/2020 | Approved | HENRY KIM |
| Insulation | 7/9/2020 | Corrections Issued | HENRY KIM |
| Insulation | 7/10/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 7/10/2020 | Approved | HENRY KIM |
| Special/Order Compliance | 7/10/2020 | Approved | HENRY KIM |
| Drywall Nailing | 7/15/2020 | Not Ready for Inspection | HENRY KIM |
| Drywall Nailing | 7/16/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 7/16/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/2/2020 | Corrections Issued | HENRY KIM |
| Final | 9/2/2020 | Corrections Issued | HENRY KIM |
| Green Building Final | 9/2/2020 | Approved | HENRY KIM |
| HVAC-Final | 9/2/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 9/2/2020 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 9/2/2020 | SGSOV Gas Company | HENRY KIM |
| Smoke Detectors | 9/2/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/14/2020 | Approved | HENRY KIM |
| Final | 9/14/2020 | Corrections Issued | HENRY KIM |