11813 W NEENACH ST 91352
Certificate Information: 11813 W NEENACH ST 91352
- Application / Permit
- 20014-20000-01224
- Plan Check / Job No.
- B20VN04585
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR SHAPED 52'6"X33'0" ADDITION AND REMODEL TO SFD
- Permit Issued
- Issued on 6/3/2021
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | MARVEL DELACRUZ |
| Corrections Issued | 4/16/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 4/17/2020 | STEVEN KIM |
| Green Plans Picked Up | 4/17/2020 | APPLICANT |
| Building Plans Picked Up | 4/24/2020 | APPLICANT |
| Applicant returned to address corrections | 11/12/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 12/3/2020 | MARVEL DELACRUZ |
| Issued | 6/3/2021 | APPLICANT |
| CofO in Progress | 9/20/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 10/15/2022 | MICHAEL SMITH |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 6/19/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 10/6/2020 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/13/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/13/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 11/17/2020 | MATTHEW CRAIG |
| ZI | Cleared | 11/18/2020 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bejarano,, David Alberto; Lic. No.: C81225 | 9740 ZELZAH AVE 237 NORTHRIDGE, CA 91325 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2021 | Corrections Issued | JOHN HAYES |
| Deputy Drilled-In Anchors | 7/16/2021 | No Access for Inspection | JOHN HAYES |
| Deputy Drilled-In Anchors | 7/19/2021 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 7/21/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/28/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/11/2021 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 8/11/2021 | Partial Approval | JOHN HAYES |
| Pre-Inspection | 8/17/2021 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/18/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/18/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/18/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/18/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 10/18/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/18/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 11/24/2021 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 11/24/2021 | Approved | MATTHEW NELSON |
| Special/Order Compliance | 11/24/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/13/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 12/13/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 12/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 12/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 1/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 1/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/10/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 5/10/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 5/10/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/10/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 5/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/10/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 5/10/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 8/10/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 8/10/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 8/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 8/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 8/10/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 8/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 9/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 9/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 9/20/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |