8005 S GEORGETOWN AVE 90045
Certificate Information: 8005 S GEORGETOWN AVE 90045
- Application / Permit
- 20014-20000-01195
- Plan Check / Job No.
- B20VN04519
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE AND CONVERT (E) 14'-16'-8" BALCONY TO BEDROOM AND CONVERT (E) 13'-5" X 9'-10" ATTIC TO CLOSET AREA ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/13/2020
- Issuing Office
- Current Status
- CofO Issued on 2/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | SEWADA ZADOORIAN MILAGARDI |
| Green Plans Picked Up | 4/9/2020 | APPLICANT |
| Corrections Issued | 4/16/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 4/22/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 4/23/2020 | APPLICANT |
| Plan Check Approved | 7/10/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 7/13/2020 | APPLICANT |
| CofO in Progress | 2/3/2021 | DAVID HEINE |
| CofO Issued | 2/17/2021 | VINCENT COTTON |
| Permit Finaled | 2/17/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2020 | DINAH GARIN |
| Sewer availability | Cleared | 4/28/2020 | DINAH GARIN |
| ZA Case | Cleared | 4/28/2020 | LAUREN PADICK |
| Green Code | Cleared | 6/5/2020 | DAVID MATSON |
| Roof/Waste drainage to street | Cleared | 7/6/2020 | ANTHONY MAINEZ |
Contact Information
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | 20720 VENTURA BLVD #280 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 9/15/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 10/7/2020 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 10/7/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 10/7/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 10/21/2020 | Approved | JUAN VALENZUELA |
| Insulation | 10/21/2020 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/21/2020 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 10/21/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 10/28/2020 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/28/2020 | Approved | JUAN VALENZUELA |
| Insulation | 11/2/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 11/10/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/30/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 12/30/2020 | Corrections Issued | JOHNNY MIRANDA |
| Final | 12/30/2020 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 12/30/2020 | Approved | JOHNNY MIRANDA |
| Green Building Final | 12/30/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 12/30/2020 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/30/2020 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 12/30/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 1/6/2021 | Approved | JOHNNY MIRANDA |
| Final | 1/6/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 1/6/2021 | Approved | JOHNNY MIRANDA |
| Final | 2/3/2021 | Conditional Approval | DAVID HEINE |